Verified PartnerAgra–Lucknow to Ganga Expressway via Farrukhabad
(आगरा–लखनऊ से गंगा एक्सप्रेसवे वाया फर्रुखाबाद)
The Agra–Lucknow to Ganga Expressway via Farrukhabad is a proposed 90.838 km six-lane greenfield access-controlled highway planned by UPEIDA under EPC contract mode with an approved project outlay of ₹7,488.74 crore. Originating from Km 0+000 at the Kudrail Interchange on the Agra–Lucknow Expressway and terminating at Km 90+838 at the Timirpur Trumpet Interchange on the Ganga Expressway, the corridor creates high-speed connectivity across central Uttar Pradesh.
Want Your Brand Featured Here?
Reach thousands of decision-makers and investors searching for infrastructure projects every month.
*Project is at the EPC tender evaluation and contractor award stage. Land acquisition proceedings active across Etawah, Mainpuri, Farrukhabad, Shahjahanpur, and Hardoi districts.
Advertisement // Sponsor
Verified PartnerAgra–Lucknow to Ganga Expressway via Farrukhabad Route Map (आगरा–लखनऊ से गंगा एक्सप्रेसवे रूट मैप)
The proposed Agra–Lucknow to Ganga Expressway Via Farrukhabad route map delineates a 90.838 km greenfield access-controlled corridor, seamlessly interconnecting the Agra–Lucknow Expressway at Km 0+000 (Kudrail Interchange) with the Ganga Expressway at Km 90+838 (Timirpur Interchange) while providing high-speed connectivity to Farrukhabad, the Sankisa Buddhist pilgrimage center, and the sacred Ganga River crossing.
Advertisement // Sponsor
Verified PartnerConstruction Status & Latest Updates (2026)
The Agra–Lucknow to Ganga Expressway via Farrukhabad is a 90.838-km six-lane greenfield access-controlled expressway developed by the Uttar Pradesh Expressways Industrial Development Authority (UPEIDA). Taking off at Km 0+000 from the Kudrail Interchange on the Agra–Lucknow Expressway (near Takha, Dist. Etawah) and terminating at Km 90+838 on the Ganga Expressway (near Timirpur, Sawajpur tehsil, Dist. Hardoi), the corridor integrates central Uttar Pradesh directly into the state's super-highway network.
Regarding the Agra–Lucknow to Ganga Expressway via Farrukhabad construction status in 2026, the project is in the advanced procurement phase with status Tender Evaluation — Financial Bids Evaluated (Contract Awards Awaiting Official Confirmation). UPEIDA officially invited EPC bids across two civil packages (Package-I and Package-II), specifying a tender-listed work completion period of 1,095 days from contract award. Financial bid evaluations identified LLC Volgadorstroi as the reported lowest bidder (L1) for Package-I (civil estimate: ₹1,964.21 Cr) and Apco Infratech Pvt. Ltd. as the reported lowest bidder (L1) for Package-II (civil estimate: ₹2,809.06 Cr). Neither firm is an officially appointed contractor until formal Letters of Award (LoA) and contract agreements are executed by UPEIDA. Total cabinet project outlay is sanctioned at ₹7,488.74 crore.
The link expressway solves a major connectivity bottleneck in Uttar Pradesh's road grid. Currently, traffic moving between western UP (Agra, Mathura, Rajasthan) and the upper northern / eastern belt (Meerut, Shahjahanpur, Moradabad, Prayagraj) must navigate congested two-lane state highways through Kannauj and Farrukhabad. By integrating seamlessly with the Ganga Expressway at Timirpur, the Agra–Lucknow to Purvanchal Link Expressway grid, the Purvanchal Expressway, and the Lucknow Kanpur Expressway, this project creates an uninterrupted express corridor across central UP while offering direct access to the famous potato trading hub of Farrukhabad and the international pilgrimage site of Sankisa.
Toll Charges & FASTag Updates (2026)
| Vehicle Category | Eligible Vehicle Types | Toll Tariff Status | Official Notified Rate |
|---|---|---|---|
| Car / Jeep / Van (LMV) | Private motor cars, jeeps, vans, compact and full-size SUVs | Pre-Construction (Under Tender) | Official Toll Rates Not Yet Notified |
| Light Commercial Vehicle (LCV) | Minibuses, light commercial delivery vans, freight tempos | Pre-Construction (Under Tender) | Official Toll Rates Not Yet Notified |
| 2-Axle Truck / Lorry | Standard 2-axle commercial freight trucks, medium goods carriers | Pre-Construction (Under Tender) | Official Toll Rates Not Yet Notified |
| Heavy Passenger Bus | Heavy passenger buses, luxury intercity motor coaches, UPSRTC | Pre-Construction (Under Tender) | Official Toll Rates Not Yet Notified |
| 3-Axle Commercial Truck | 3-axle commercial freight carriers and heavy cargo vehicles | Pre-Construction (Under Tender) | Official Toll Rates Not Yet Notified |
| Multi-Axle Vehicle (MAV / HCM) | Heavy construction machinery, multi-axle freight trailers (4-6+ axles) | Pre-Construction (Under Tender) | Official Toll Rates Not Yet Notified |
100% Cashless FASTag Architecture Planned
Tender technical requirements specify automated FASTag RFID toll collection across all entry and exit lanes to maintain high-speed corridor throughput once constructed.
Distance-Proportional Tolling Plan
The DPR plans a closed toll collection system with mainline barrier plazas at Km 05+300 and Km 85+900 plus interchange ramp booths, ensuring motorists pay strictly for the actual distance travelled.
No Tolls Active Currently
As the project is under tender evaluation, no toll charges, toll booths, or electronic toll plazas are currently operational. Toll schedules will be finalized post-construction.
Speed Limit & Traffic Rules
| Vehicle Classification (MoRTH) | Engineering Design Speed (IRC:SP:99) | Operational Speed Limit Status | Proposed ATMS / Surveillance (Planned) |
|---|---|---|---|
| Passenger Cars & SUVs (M1 Category, ≤ 8 seats) | 120 km/h (Proposed Design Speed) | Official Operational Speed Limits Not Yet Notified | Proposed ATMS radar gantries & sectional surveillance (planned post-commissioning) |
| Commercial Goods Carriers & Trucks (N2 / N3) | 80 km/h (Proposed Design Speed) | Official Operational Speed Limits Not Yet Notified | Proposed freight lane-discipline monitoring (planned post-commissioning) |
| Heavy Passenger Buses (M2 / M3 Categories) | 100 km/h (Proposed Design Speed) | Official Operational Speed Limits Not Yet Notified | Proposed speed monitoring & lane regulation (planned post-commissioning) |
120 km/h Proposed Engineering Design Speed & 120m RoW
As specified under IRC:SP:99-2023(Manual of Specifications and Standards for Expressways), the corridor is planned with horizontal curve radii (>1,000 meters) and gentle vertical gradients supporting a 120 km/h proposed geometric design speed. The 120-meter Right of Way provides 60 meters on either side of the centerline, including a 26-meter median reservation for future expansion from 6 to 8 lanes.
Under proposed expressway access-control regulations, slow-moving vehicles such as two-wheelers, auto-rickshaws, tractors, and non-motorized transport are planned to be restricted from mainline carriageways through boundary fencing and grade-separated entry points.
Farrukhabad Potato Heartland: Connectivity, Transit & Pilgrimage
The link expressway resolves a critical missing link across Uttar Pradesh's high-speed grid. Farrukhabad is India's leading potato cultivation and cold-storage hub; the corridor will dramatically reduce transit times for agricultural freight moving to consumption markets in the National Capital Region (NCR), Kanpur, and eastern India.
The expressway will also catalyze spiritual and cultural tourism by providing direct, high-speed access to the ancient Buddhist / Jain pilgrimage stupas of Sankisa (via Km 33+715 interchange) and the renowned ashram of Neem Karori Dham (via Km 65+307 interchange).
Interchanges, River Bridges & Engineering Plan
As detailed in the official UPEIDA EPC tender notices, the project is divided into two distinct construction packages:
- ▸Package-I (Km 0+000 to Km 50+000): From Kudrail Interchange on Agra–Lucknow Expressway (Etawah/Mainpuri) to Village Kataiya (Farrukhabad). Length: 50.000 km. Base civil estimate: ₹1,964.21 crore. Reported L1 Bidder: LLC Volgadorstroi (~₹1,914.71 crore; awaiting formal contract award).
- ▸Package-II (Km 50+000 to Km 90+838): From Village Kataiya (Farrukhabad) to Timirpur Interchange on Ganga Expressway (Hardoi). Length: 40.838 km. Base civil estimate: ₹2,809.06 crore. Encompasses the 2.82 km Ganga River Bridge and 200m Ramganga Bridge. Reported L1 Bidder: Apco Infratech Pvt. Ltd. (~₹2,894.00 crore; awaiting formal contract award).
- ▸Tender-Listed Work Period: 1,095 days (approx. 3 years) from the Appointed Date following formal contract award.
- ▸Corridor Take-off Point: Km 00+000 at Kudrail Cloverleaf Interchange on Agra–Lucknow Expressway (Takha, Etawah / Mainpuri border).
- ▸Corridor Terminal Point: Km 90+838 at Timirpur Trumpet Interchange at Ganga Expressway Ch 282+845 (Sawajpur, Hardoi).
The Detailed Project Report (DPR) outlines a 6-lane access-controlled expressway expandable to 8 lanes with comprehensive grade-separation:
- ▸Right of Way: 120-meter Right of Way with a 26-meter median reservation designed for future expansion from 6 to 8 lanes.
- ▸Major Ganga River Bridge: 2.82 km long 6-lane major bridge across the Ganga River at Km 75+425 engineered with 47 PSC I-girder spans of 60 meters each.
- ▸Major Ramganga River Bridge: 200m long 4-span bridge (4x50m) across the Ramganga River at Km 86+930 with 29° skew.
- ▸Railway Overbridges (ROBs): Major steel bowstring girder ROB at Km 46+955 (1x20m+1x72m+1x20m, 43° skew) over Northern Railway mainline tracks, and ROB at Km 66+085 (1x45m, 18° skew).
- ▸Wayside Amenities & Tolling: Mainline toll plazas at Km 05+300 & Km 85+900, intermediate barrier at Km 50+310, and planned WSA complexes for fuel and rest stops.
Advertisement // Sponsor
Verified PartnerExpressway Length, Project Cost & Specifications
| Parameter | Technical Specification |
|---|---|
| Official Project Name | Development of Agra-Lucknow Expressway to Ganga Expressway via Farrukhabad Link Expressway |
| Total Corridor Length | 90.838 km (Greenfield access-controlled alignment, Km 0+000 to Km 90+838) |
| Toll Tariff Status | Official Toll Rates Not Yet Notified |
| Speed Regulations | 120 km/h proposed geometric design speed (IRC:SP:99-2023); official operational speed limits not yet notified |
| Major Interchanges | Grade-separated trumpet & cloverleaf interchanges planned at terminal expressways (Agra–Lucknow & Ganga) and key highway intersections (Sankisa, SH-40, NH-730C, Farrukhabad-Aliganj link) |
| Estimated Project Cost | ₹7,488.74 crore (Reported Cabinet-Approved Project Estimate) |
| Implementing Authority | Uttar Pradesh Expressways Industrial Development Authority (UPEIDA) |
| Contract Mode | EPC (Engineering, Procurement, and Construction) |
| Tender Structure | 2 EPC Civil Packages (Package-I & Package-II) |
| Tender-Listed Work Period | 1,095 days (from appointed date post contract award) |
| Corridor Width / RoW | 6 lanes, expandable to 8 lanes (120 m Right of Way with 26m median) |
| Corridor Start Point | Km 0+000 Kudrail Interchange (Cloverleaf) on Agra–Lucknow Expressway (Takha, Dist. Etawah / Mainpuri border) |
| Corridor End Point | Km 90+838 Timirpur Trumpet Interchange at Ganga Expressway Ch 282+845 (Sawajpur, Dist. Hardoi) |
| Major Bridges & ROBs | 2.82 km Ganga River Bridge (Km 75+425, 47x60m spans), 200m Ramganga River Bridge (Km 86+930, 4x50m spans), and two railway overbridges (Km 46+955 & Km 66+085) |
| Wayside Amenities (WSAs) | Planned wayside amenity complexes along the alignment (fuel, EV charging plazas, rest areas) |
| Last Data Audit | Last Verified: October 2026 |
| Current Project Status | Tendering & Land Acquisition Stage |
| Commercial Commissioning / Completion | 1,095 Days (Tender-Listed Work Period; Opening Date TBA Post-Award) |
Project Chronology & Tender Milestones
Corridor Conceptualization & Feasibility Alignment
Government of Uttar Pradesh and UPEIDA conceptualized a 6-lane access-controlled greenfield expressway link to bridge the Agra–Lucknow and Ganga Expressways through the agrarian heartland of Farrukhabad.
DPR Finalization & 120m RoW Engineering Surveys
Detailed Project Report (DPR) established the exact 90.838 km alignment with a 120-meter Right of Way, landmark 2.82 km Ganga River crossing, 200m Ramganga River bridge, and 2 major railway overbridges.
UPEIDA EPC Tenders Floated (Package-I & Package-II)
UPEIDA officially issued Requests for Proposal for Package-I (civil estimate ₹1,964.21 Cr) and Package-II (civil estimate ₹2,809.06 Cr) specifying 1,095 days work period.
Statutory Land Acquisition Notifications
Competent revenue authorities issued Section 3A/3D equivalent land acquisition notifications across designated villages in Etawah, Mainpuri, Farrukhabad, Shahjahanpur, and Hardoi districts.
Financial Bid Evaluations & L1 Bidder Determination
Technical evaluations completed and financial bids opened. LLC Volgadorstroi emerged as the evaluated lowest bidder (L1) for Package-I (₹1,914.71 Cr), and Apco Infratech Pvt. Ltd. emerged as L1 for Package-II (₹2,894.00 Cr). Formal contract awards and appointed date notifications remain pending confirmation.
Civil Construction & River Bridge Execution (1,095 Days)
Contractually stipulated construction period of 1,095 days from the Appointed Date post-award, covering 90.838 km carriageways, Ganga and Ramganga river bridges, and intelligent traffic management systems.
All technical parameters, corridor alignments, chainages, and tender milestones on this page are cross-verified against official statutory notifications and engineering records:
Package-I Civil Works (Kudrail to Kataiya)
Civil construction of 6-lane access-controlled expressway from Kudrail (Ch 0+000) to Kataiya (Ch 50+000). Base civil estimate: ₹1,964.21 Cr; completion period: 1,095 days.
Package-II Civil Works (Kataiya to Timirpur)
Civil construction of 6-lane access-controlled expressway from Kataiya (Ch 50+000) to Timirpur (Ch 90+838), including 2.82 km Ganga River Bridge and 200m Ramganga Bridge. Base civil estimate: ₹2,809.06 Cr.
Approved Project Outlay: ₹7,488.74 Crore
Comprehensive financial sanction covering civil construction, utility shifting, environmental clearances, and land acquisition across Etawah, Mainpuri, Farrukhabad, Shahjahanpur, and Hardoi districts.
IRC:SP:99-2023 (Expressway Manual)
Manual of Specifications and Standards for Expressways governing 120 km/h proposed geometric design speed, 120-meter Right of Way, grade-separated trumpet/cloverleaf interchanges, and access control.
Advertisement // Sponsor
Verified PartnerFrequently Asked Questions (FAQs)
Related Infrastructure Projects
Ganga Expressway
A major 594 km greenfield access-controlled expressway connecting Meerut and Prayagraj in Uttar Pradesh.
View Project →Agra–Lucknow to Purvanchal Expressway Link Expressway
A 50.940 km 6-lane (expandable to 8-lane) access-controlled greenfield expressway by UPEIDA directly connecting the Agra-Lucknow and Purvanchal Expressways south of Lucknow.
View Project →Purvanchal Expressway
A fully operational 6-lane access-controlled expressway connecting Lucknow to Ghazipur in eastern Uttar Pradesh.
View Project →Lucknow–Kanpur Expressway
An advanced 63 km corridor (NE-6 / Awadh Expressway) slashing travel times between Lucknow and Kanpur to 45 minutes.