Verified PartnerWayanad Tunnel Project: Anakampoyil Kalladi Meppadi Tunnel Road Route Map, Latest Update & Status (2026)
The Anakampoyil–Kalladi–Meppadi Tunnel Road is a planned 8.7 km long twin-tube underground road tunnel connecting Anakampoyil in Kozhikode district directly to Meppadi in Wayanad district. Excavated through the Western Ghats by Konkan Railway Corporation (KRCL), it provides an all-weather alternative bypassing the landslide-prone Thamarassery Churam pass.
"Following final environmental and financial clearances granted in February 2026, the Rs 2,134.5 crore Anakkampoyil-Meppadi Tunnel Road project has transitioned into active construction. Night shifts commenced in June, with significant progress now observed at Tunnel Portal 1 as of early July."
ആനക്കാംപൊയിൽ–കള്ളാടി–മേപ്പാടി തുരങ്കപ്പാത (Wayanad Tunnel Road)
കോഴിക്കോട് ജില്ലയിലെ ആനക്കാംപൊയിലിനെ വയനാട് ജില്ലയിലെ മേപ്പാടിയുമായി ബന്ധിപ്പിക്കുന്ന 8.7 കിലോമീറ്റർ നീളമുള്ള ഇരട്ട തുരങ്കപ്പാത താമരശ്ശേരി ചുരത്തിലെ ഗതാഗതക്കുരുക്കിന് ശാശ്വത പരിഹാരമായി കൊങ്കൺ റെയിൽവേ നിർമ്മിക്കുന്നു.
Want Your Brand Featured Here?
Reach thousands of decision-makers and investors searching for infrastructure projects every month.
Wayanad Tunnel Project Route Map
View and download the latest Anakampoyil Kalladi Meppadi Tunnel Road route map showing the project alignment, major junctions, districts covered and connectivity corridors.
Advertisement // Sponsor
Verified PartnerAdvertisement // Sponsor
Verified PartnerAnakampoyil Kalladi Meppadi Tunnel RoadCost • Route • Timeline
| Parameter | Technical Details |
|---|---|
| Project Name | Anakampoyil Kalladi Meppadi Tunnel Road |
| Total Length | 8.7 km |
| Estimated Cost | ₹2,100 Crore |
| Expected Completion Date | 2029 (Proposed) |
| Total Packages | 1 Package |
Advertisement // Sponsor
Verified PartnerLatest Developments
Video Updates
Advertisement // Sponsor
Verified PartnerFrequently Asked Questions
The Anakkampoyil–Kalladi–Meppadi Tunnel Road is a twin-tube, four-lane road project connecting Kozhikode and Wayanad through the Western Ghats. The project is being implemented through Konkan Railway Corporation Limited (KRCL) and includes tunnel, bridge and four-lane approach-road works. The overall project cost is ₹2,134.50 crore.
The route connects Anakkampoyil and Marippuzha in Kozhikode district with Kalladi near Meppadi in Wayanad. The alignment uses the existing Anakkampoyil–Muthappanpuzha–Marippuzha side and connects through the tunnel to the Kalladi–Meppadi side, providing an alternative to the existing ghat-road connection.
The project alignment runs from the Marippuzha side in Kozhikode towards Kalladi in Wayanad. The route includes a four-lane approach, a bridge across the Iruvanjippuzha near Marippuzha and the twin-tube tunnel through the Western Ghats before connecting to the Meppadi–Kalladi side.
The project alignment is approximately 8.73 km long. Kerala Government information gives 8.73 km for the road, including about 8.1 km of twin-tunnel section. Contract documentation specifies the Package-II tunnel-road section from Km 0.460 to Km 8.735, with a package project length of 8.275 km.
The estimated overall cost of the Anakkampoyil–Kalladi–Meppadi tunnel road project is ₹2,134.50 crore. The tunnel-road construction package itself was awarded for ₹1,341 crore including GST, so the package value should not be confused with the total project cost.
Construction has started, but the tunnel works are currently suspended following a fatal landslide near the Kalladi construction area in July 2026. Before the suspension, excavation had progressed from the Anakkampoyil side, with the right tunnel reaching about 75 metres by early July. The Kerala Government ordered investigations into the landslide and project safety.
A major recent development is the grant of Stage-II final forest clearance by the Ministry of Environment, Forest and Climate Change in September 2026. However, construction has not yet resumed after the July 2026 Kalladi landslide, and an expert committee report on the incident was still awaited in September.
Tunnel construction was suspended after a landslide near the Kalladi project site in July 2026 caused multiple fatalities. The Kerala Government ordered separate investigations into the incident, geological and technical risks, and whether the contractor complied with the environmental conditions attached to the project's clearance.
The project is designed as a four-lane road with two separate tunnel tubes, providing two traffic lanes in each direction. The tunnel package is formally described as a twin-tube unidirectional tunnel with two lanes in each traffic direction, together with four-lane approach roads.
The tunnel-road construction package has a contractual execution period of 48 months. However, the project does not currently have a reliable firm completion date because construction was suspended after the July 2026 landslide and the resumption depends on the findings of the ongoing safety and technical investigations.
Related Infrastructure Projects
Kochi Metro
A rapid transit system serving Kochi, currently constructing the Phase 2 Pink Line Kakkanad extension.
View Project →Bangalore Malappuram Highway
A proposed high-speed greenfield corridor connecting Karnataka and Kerala, easing inter-state transit.
View Project →Thiruvananthapuram Outer Ring Road (NH-866)
A 62.7 km 4-lane access-controlled greenfield ring highway (NH-866, ₹8,004.72 Cr NHAI tender value) connecting Navaikulam to Vizhinjam via Kilimanoor, Thekkada, and Nedumangad.