Verified PartnerMumbai Metro Line 3 (Cuffe Parade - SEEPZ) Route Map, Stations & Status
Mumbai Metro Line 3 (Aqua Line / Colaba Bandra SEEPZ Metro / Colaba SEEPZ Metro) is Mumbai's premier 33.5 km Mumbai Underground Metro corridor connecting Cuffe Parade in South Mumbai to Aarey JVLR in the Northern Suburbs via Nariman Point, CSMT, Worli, Dadar, Bandra-Kurla Complex (BKC), MIDC SEEPZ, and Chhatrapati Shivaji Maharaj International Airport (CSMIA T1 & T2). Implemented and operated by Mumbai Metro Rail Corporation Limited (MMRC), Phase 1 (Aarey JVLR to BKC, 12.69 km) opened on 5 October 2024. Explore the Metro Line 3 Route, Metro Line 3 Stations, Mumbai Metro Line 3 Opening Date updates, fare, and timings.
Want Your Brand Featured Here?
Reach thousands of decision-makers and investors searching for infrastructure projects every month.
Mumbai Metro Line 3 (Cuffe Parade - SEEPZ) Economics
Expected Completion Date
Mumbai Metro Line 3 (Cuffe Parade - SEEPZ) Stations
| # | Station | Type | Interchange / Connection | Opened |
|---|---|---|---|---|
| 01 | Cuffe Parade | Terminal | — | Under Advanced Testing |
| 02 | Vidhan Bhavan | Regular | — | Under Advanced Testing |
| 03 | Churchgate | Interchange | Western Railway (Churchgate) | Under Advanced Testing |
| 04 | Hutatma Chowk | Regular | — | Under Advanced Testing |
| 05 | CSMT | Interchange | Central Railway & Outstation Trains (CSMT) | Under Advanced Testing |
| 06 | Kalbadevi | Regular | — | Under Advanced Testing |
| 07 | Girgaon | Regular | — | Under Advanced Testing |
| 08 | Grant Road | Interchange | Western Railway (Grant Road) | Under Advanced Testing |
| 09 | Mumbai Central | Interchange | Western Railway (Mumbai Central) | Under Advanced Testing |
| 10 | Mahalaxmi | Interchange | Western Railway (Mumbai Central/Mahalaxmi area) | Under Advanced Testing |
| 11 | Science Museum | Regular | — | Under Advanced Testing |
| 12 | Acharya Atre Chowk | Regular | — | Under Advanced Testing |
| 13 | Worli | Regular | — | Under Advanced Testing |
| 14 | Siddhivinayak | Regular | — | Under Advanced Testing |
| 15 | Dadar | Interchange | Western Railway & Central Railway (Dadar) | Under Advanced Testing |
| 16 | Shitladevi | Regular | — | Under Advanced Testing |
| 17 | Dharavi | Regular | — | Under Advanced Testing |
| 18 | BKC (Bandra Kurla Complex) | Terminal / Interchange | Line 2B (BKC) | 2024 |
| 19 | Vidyanagari | Regular | Mumbai University Kalina | 2024 |
| 20 | Santacruz | Interchange | Western Railway (Santacruz) | 2024 |
| 21 | CSMIA T1 | Interchange | Domestic Airport Terminal 1 | 2024 |
| 22 | Sahar Road | Regular | — | 2024 |
| 23 | CSMIA T2 | Interchange | International Airport Terminal 2 & Line 7A | 2024 |
| 24 | Marol Naka | Interchange | Line 1 (Blue Line) | 2024 |
| 25 | MIDC | Regular | — | 2024 |
| 26 | SEEPZ | Regular | — | 2024 |
| 27 | Aarey JVLR | Terminal | Line 6 (Pink Line) & Aarey Depot | 2024 |
Mumbai Metro Line 3 (Cuffe Parade - SEEPZ) Route Map
Advertisement // Sponsor
Verified PartnerAdvertisement // Sponsor
Verified PartnerMumbai Metro Line 3 (Cuffe Parade - SEEPZ) Technical Specifications
| Parameter | Value |
|---|---|
| Estimated Cost | 37276.0 |
| Corridor Type | Underground (33.0 km Twin Tunnels + 0.5 km At-Grade) |
| Primary Depot | Aarey Depot (Aarey Colony, 25 Hectares) |
| Track Gauge | Standard Gauge (1435 mm) |
| Total Length | 33.5 km |
| Opened / Est. Opening | Phase 1 Operational (Opened 5 October 2024); remaining section under testing / commissioning |
| Corridor Status | Partially Operational |
| Maximum Design Speed | 95 km/h (Design) / 80 km/h (Operating) |
| Operator | Mumbai Metro Rail Corporation Limited (MMRC) |
| Stations Count | 27 |
| Line Number | 3 (Aqua Line) |
| Electrification System | 25kV AC Rigid Overhead Conductor System (ROCS) |
Mumbai Metro Line 3 (Cuffe Parade - SEEPZ) Timeline
Approved by Cabinet of India; JICA loan agreement signed for ~57% project funding
17 Tunnel Boring Machines (TBMs) deployed across 7 tunneling packages
100% Tunneling completed across 54.5 km of twin underground tunnels
Phase 1 (Aarey JVLR to BKC, 12.69 km, 10 stations) inaugurated by Prime Minister Narendra Modi
Phase 2A (BKC–Acharya Atre Chowk) opened; final phase testing / commissioning in progress
Phase 1 Operational (Opened 5 October 2024); remaining section under testing / commissioning
Mumbai Metro Line 3 (Cuffe Parade - SEEPZ) Economic & Connectivity Impact
Economic Significance
Cuts travel time between South Mumbai (Cuffe Parade/CSMT) and International Airport (T2) / BKC from 90+ minutes to 35 minutes on the Mumbai Metro Aqua Line.
Traffic Impact
Projected daily ridership exceeds 12 lakh after full corridor commissioning across South Mumbai, BKC, and Western Suburbs.
Employment Centres Served
Provides direct seamless Mumbai Underground Metro transit to Nariman Point, CSMT, Worli, BKC, SEEPZ, and CSIA Airport.
Intermodal Connectivity
First fully underground mega-transit backbone of Mumbai connecting 6 suburban railway hubs and both airport terminals.
Impact on Real Estate
Catalyzing massive transit-oriented commercial redevelopments across Worli, Dadar, Kalina, and BKC.
Mumbai Metro Line 3 (Cuffe Parade - SEEPZ) Alignment Map & GIS Explorer
Advertisement // Sponsor
Verified PartnerAdvertisement // Sponsor
Verified PartnerFrequently Asked Questions
Advertisement // Sponsor
Verified PartnerEnjoy tracking infrastructure projects?
Get monthly updates whenever major Indian infrastructure projects move forward.