Verified PartnerMumbai–Ahmedabad High-Speed Rail (MAHSR): Route Map, Stations, Status & Latest Update
मुंबई-अहमदाबाद हाय-स्पीड रेल / મુંબઈ-અમદાવાદ હાઇ-સ્પીડ રેલ (બુલેટ ટ્રેન)
The Mumbai–Ahmedabad High-Speed Rail (MAHSR) corridor is India's flagship 508 km bullet train project connecting Mumbai with Ahmedabad. Operating at speeds up to 320 km/h using Japanese Shinkansen E5 series technology, the project slashes travel time between Bandra Kurla Complex (BKC) and Sabarmati to approximately 2 hours, featuring India's first 21 km undersea tunnel beneath Thane Creek.
The Mumbai–Ahmedabad High-Speed Rail Corridor project has made significant progress with all 14 portal beams now installed over the Rajdhani route in Vadodara. The completion of the 371 km viaduct and installation of over 9,300 overhead electrical masts indicate ongoing construction milestones. Despite initial concerns about meeting timelines, the project appears to be progressing steadily with key structural hurdles overcome, including the installation of portal beams on the Delhi–Mumbai Rajdhani main line. The project remains a flagship rail infrastructure initiative in India's ambitious plan for high-speed rail connectivity.
Want Your Brand Featured Here?
Reach thousands of decision-makers and investors searching for infrastructure projects every month.
Mumbai–Ahmedabad High-Speed Rail CorridorRoute Map & Alignment
View and download the latest Mumbai–Ahmedabad High-Speed Rail Corridor route map showing the project alignment, major junctions, districts covered and connectivity corridors.
Advertisement // Sponsor
Verified PartnerAdvertisement // Sponsor
Verified PartnerMumbai–Ahmedabad High-Speed Rail CorridorCost • Route • Timeline
| Parameter | Technical Details |
|---|---|
| Project Name | Mumbai–Ahmedabad High-Speed Rail Corridor |
| Total Length | 508 km |
| Estimated Cost | ₹1,08,000 Crore |
| Implementing Authority | National High Speed Rail Corporation Limited (NHSRCL) |
| Districts Covered | Mumbai, Thane, Palghar (Maharashtra); Dadra & Nagar Haveli (UT); Valsad, Navsari, Surat, Bharuch, Vadodara, Anand, Kheda, Ahmedabad (Gujarat) |
| Number of Villages Affected | Land acquisition spans more than 100 villages across Maharashtra and Gujarat |
| Current Phase | Under Construction / Execution |
| Start Date | Groundbreaking: September 2017 | Construction: February 2021 |
| Expected Completion Date | 2028 |
| Total Packages | 11 Packages |
| Track Gauge | 1,435 mm (Standard Gauge) |
| Rolling Stock | B28 (Vande Bullet) and E10 Series Shinkansen |
| Current Status | Under Construction / Execution |
| Operating Speed | 320 km/h |
| Max Design Speed | 350 km/h |
| Target Completion | 2028 |
| Maintenance Depots | 3 Depots (Sabarmati, Surat, Thane) |
| Signalling & Control | Digital Automatic Train Control (DS-ATC / Shinkansen ATC system) |
| Alignment Composition | 460.3 km Viaducts (90.6%), 25.87 km Tunnels (including 7 km undersea), 12.9 km Embankments (2.5%), 9.22 km Bridges (1.8%) |
| Electrification System | 25 kV 50 Hz AC overhead |
| Number of HSR Stations | 12 Stations |
| Project Implementation | National High Speed Rail Corporation Limited (NHSRCL) |
MAHSR Technical Specifications & Features
The project incorporates state-of-the-art high-speed rail design elements:
- Viaduct Alignment: The alignment consists of 460.3 km of elevated viaducts (90.6% of the route), 25.87 km of tunnels (5.1%), 12.9 km of embankments (2.5%), and 9.22 km of bridges (1.8%).
- Bridges & River Crossings: The route includes multiple specialized bridges spanning key rivers across Gujarat and Maharashtra.
- Rolling Stock: Current plans envisage initial services using indigenous B28 (Vande Bullet) trainsets, followed by the introduction of E10 Series Shinkansen trainsets. Both Business Class and Standard Class accommodations will be offered.
- Power & Systems: Electrified via a 25 kV 50 Hz AC overhead traction system and controlled by Digital Automatic Train Control (DS-ATC / Shinkansen ATC system).
- Operation Control: Supported by the central Sabarmati Operation Control Centre (OCC) to monitor all train movements and systems.
- Depots: Supported by three rolling stock maintenance depots located at Sabarmati, Surat, and Thane.
- Capacity & Ridership: Planned for 70 train services per day, with an initial projected daily ridership of 36,000 passengers (based on initial DPR estimates).
- Slab Track & Safety: Deploys advanced slab track technology (J-Slab) and automated seismometer-linked earthquake early warning systems.
Mumbai Ahmedabad Bullet Train Stations
The corridor features 12 designated high-speed stations strategically placed to serve key cities and business centers. The stations include Mumbai (BKC), Thane, Virar, and Boisar in Maharashtra; and Vapi, Bilimora, Surat, Bharuch, Vadodara, Anand, Ahmedabad, and Sabarmati in Gujarat.
The underground Bandra Kurla Complex (BKC) station box will be an underground station (NHSRCL designs designate it as India's deepest HSR station box), featuring a multi-level structure with six platforms built entirely below ground level. Sabarmati will serve as a major multi-modal hub, integrating the bullet train with Indian Railways, local metros, and bus transport systems.
India's First Undersea Rail Tunnel
A major engineering feat of the project is the construction of a 21 km underground tunnel in Maharashtra, stretching along the BKC–Shilphata route. This 21 km underground section includes a 7 km segment beneath Thane Creek, forming India's first undersea rail tunnel. Package C2, which covers this tunnel section, is being built by Afcons Infrastructure using specialized Tunnel Boring Machines (TBMs) and New Austrian Tunneling Method (NATM) excavation.
Project Funding and JICA Loan
The total estimated cost of the MAHSR project is ₹1.8 lakh crore. The project is heavily supported by the Government of Japan through the Japan International Cooperation Agency (JICA), which is funding 81% of the project via a soft loan at a highly concessionary 0.1% interest rate with a 50-year repayment period (including a 15-year grace period). The National High Speed Rail Corporation Limited (NHSRCL) is the implementing body managing all construction packages.
Construction Progress and Target Timeline
Construction is moving at a rapid pace across both states. Gujarat has completed 100% land acquisition and large-scale viaduct, bridge and station construction is underway, with pier casting and viaduct erection visible across hundreds of kilometers. While Maharashtra faced land acquisition delays in early stages, 100% of the land has now been handed over, and work on BKC station (Package C1) and the undersea tunnel (Package C2) is under active execution. NHSRCL targets trial runs and a phased opening on the initial Gujarat section (Surat–Bilimora on 15 August 2027, followed by Vapi–Surat, Vapi–Ahmedabad, and the full corridor target by 2029).
Advertisement // Sponsor
Verified PartnerLatest Developments
Video Updates
Advertisement // Sponsor
Verified PartnerFrequently Asked Questions
The Mumbai Ahmedabad High Speed Rail (MAHSR) project is India's first dedicated high-speed rail corridor, commonly called the Mumbai Ahmedabad Bullet Train. The 508 km corridor is being implemented by the National High Speed Rail Corporation Limited (NHSRCL) with Japanese technical and financial assistance and will connect Mumbai with Ahmedabad through Maharashtra, Gujarat and Dadra & Nagar Haveli.
The Mumbai Ahmedabad bullet train route runs from Mumbai through Thane, Virar, Boisar, Vapi, Bilimora, Surat, Bharuch, Vadodara, Anand and Ahmedabad, terminating at Sabarmati. The corridor passes through Maharashtra, Gujarat and Dadra & Nagar Haveli.
The official Mumbai Ahmedabad bullet train alignment runs for about 508 km between Mumbai and Sabarmati/Ahmedabad, with 12 planned stations. The official NHSRCL project information identifies the station sequence and corridor alignment; detailed alignment maps should be based on the latest NHSRCL project documents rather than older proposed maps.
There are 12 planned stations: Mumbai (BKC), Thane, Virar, Boisar, Vapi, Bilimora, Surat, Bharuch, Vadodara, Anand/Nadiad, Ahmedabad and Sabarmati. Eight are in Gujarat and four are in Maharashtra.
The Mumbai Ahmedabad High Speed Rail corridor has a total alignment of approximately 508 km. NHSRCL specifies about 348 km in Gujarat, 4 km in Dadra & Nagar Haveli and 156 km in Maharashtra.
The corridor is designed for a maximum operating speed of 320 km/h. A limited-stop Mumbai-Sabarmati journey is planned to take about 2 hours 7 minutes, while a service stopping at all 12 stations is planned to take about 2 hours 58 minutes.
The originally published NHSRCL project estimate was ₹1.08 lakh crore excluding taxes. In August 2026, reports said a revised estimate of roughly ₹2.0–2.1 lakh crore had been proposed for approval, reflecting cost escalation from delays and other project factors. Because the revised figure was reported as a proposal rather than a clearly published final sanctioned cost, it should not be treated as the definitive final project cost without a subsequent official approval.
The Mumbai Ahmedabad bullet train is under active construction. By March 2026, 430 km of pier work, 341 km of girder work, 174 km of track-bed construction and 153 km of OHE mast installation had been reported. Construction has also advanced on stations, bridges, tunnels, track and electrification, with major works continuing particularly in Maharashtra.
Recent construction milestones include the start of the second tunnel-boring machine beneath Thane Creek in July 2026, progress on the 21 km Mumbai underground tunnel, continued track and electrification works, and major viaduct and bridge construction. The project is therefore in an advanced construction phase rather than merely being proposed or awaiting approval.
The latest 2026 reporting indicates that an initial section is targeted for commercial operation in 2027, while the entire Mumbai-Ahmedabad corridor is expected to take longer. August 2026 reports indicated a possible first operational section around August 2027 and full-corridor completion around 2030, but these dates should be treated as current reported targets rather than guaranteed commissioning dates.
A final official passenger fare for the Mumbai Ahmedabad bullet train has not been published by NHSRCL in its current project information. Therefore, commonly circulated ticket-price figures should not be presented as confirmed fares. The final bullet train fare is expected to be announced closer to commercial operations.
Mumbai Ahmedabad bullet train ticket booking is not yet open because commercial passenger service has not started. The booking system, fare structure and reservation details will need to be announced by the operating authority before passenger services begin. Current project information confirms that the corridor is still under construction.
The Mumbai Ahmedabad bullet train is a dedicated high-speed rail corridor with purpose-built infrastructure and a maximum operating speed of 320 km/h. Regular Mumbai to Ahmedabad trains use the conventional railway network and are separate from the MAHSR project. The bullet train is therefore a new high-speed service, not simply a faster conventional train operating on the existing railway line.
Yes. The Mumbai section includes a 21 km underground tunnel between BKC and Shilphata, including a 7 km undersea section beneath Thane Creek. In July 2026, the second tunnel-boring machine began excavation from Sawli towards Vikhroli. This will be India's first undersea rail tunnel.
The Mumbai Ahmedabad High Speed Rail corridor is being developed as a dedicated high-speed railway with a maximum operating speed of 320 km/h. Its electrification uses a 2×25 kV overhead traction system, while the alignment incorporates elevated viaducts, tunnels, bridges, dedicated stations and advanced signalling and railway systems.
The Mumbai Ahmedabad corridor is India's first high-speed rail project under execution and is intended to establish engineering, construction, operational and manufacturing capabilities for future high-speed rail corridors. Its infrastructure includes India's first undersea rail tunnel and advanced high-speed electrification, making it an important reference project for India's future HSR network.
Related Infrastructure Projects
Mumbai–Hyderabad High-Speed Rail
A ~671 km high-speed rail corridor at 320 km/h connecting India's financial capital to Hyderabad via Pune.
View Project →High-Speed Rail Network (India)
India's comprehensive high-speed and semi-high-speed rail network linking Delhi, Mumbai, Chennai, and Kolkata under the Diamond Quadrilateral program.