Fully Operational📏 29 km🚉 27 Stations Stations🗓 29 November 2017🏢 HMRL (100% Equity Owner) | L&TMRHL & Keolis (Operations & Maintenance)

The Hyderabad Metro Red Line (Corridor I) is a 29 km fully elevated mass rapid transit corridor running from Miyapur in the north-west to LB Nagar in the south-east across 27 stations. Following the 2026 state takeover, the Telangana Government holds 100% equity in Hyderabad Metro Rail Limited (HMRL), while operations and maintenance are handled by L&TMRHL and Keolis. Serving key commercial and residential hubs, the Red Line features two major metro-to-metro interchange stations at Ameerpet (Line III Blue Line) and MGBS (Line II Green Line). Commuters can also access South Central Railway (SCR) MMTS suburban rail services at Bharat Nagar, Khairatabad, and Malakpet, as well as main line train services at Hyderabad Deccan Railway Station (Nampally). HMRL states that end-to-end travel from Miyapur to LB Nagar takes approximately 45 minutes. Operational timings are from 06:00 to 23:00 daily from terminal stations, with train frequencies between 3 to 7 minutes.

FEATURED PARTNER
ADVERTISEMENT

Want Your Brand Featured Here?

Reach thousands of decision-makers and investors searching for infrastructure projects every month.

YOUR BRAND HEREPrime Infrastructure Placement
Hyderabad Metro Red Line (Line I) Economics

Hyderabad Metro Red Line (Line I) Economics

Total InvestmentHyderabad Metro Phase I — approximately ₹14,172 crore
Primary BackersState Government Owned (HMRL)
Operator / ModelState Government Ownership (HMRL) | Operations & Maintenance by L&TMRHL & Keolis
Station list

Hyderabad Metro Red Line (Line I) Stations

#StationTypeInterchange / ConnectionOpened
01
Miyapur
Terminal / Depot LinkMiyapur Depot29 November 2017
02
JNTU College
Regular—29 November 2017
03
KPHB Colony
Regular—29 November 2017
04
Kukatpally
Regular—29 November 2017
05
Balanagar
Regular—29 November 2017
06
Moosapet
Regular—29 November 2017
07
Bharat Nagar
RegularSCR MMTS Suburban Rail Link29 November 2017
08
Erragadda
Regular—29 November 2017
09
ESI Hospital
Regular—29 November 2017
10
SR Nagar
Regular—29 November 2017
11
Ameerpet
Major Metro InterchangeLine III Blue Line29 November 2017
12
Punjagutta
Regular—24 September 2018
13
Irrum Manzil
Regular—24 September 2018
14
Khairatabad
RegularSCR MMTS Suburban Rail Link24 September 2018
15
Lakdikapul
Regular—24 September 2018
16
Assembly
Regular—24 September 2018
17
Nampally
RegularHyderabad Deccan Railway Station Link24 September 2018
18
Gandhi Bhavan
Regular—24 September 2018
19
Osmania Medical College
Regular—24 September 2018
20
MGBS
Major Metro InterchangeLine II Green Line & TSRTC Bus Station24 September 2018
21
Malakpet
RegularSCR MMTS Suburban Rail Link24 September 2018
22
New Market
Regular—24 September 2018
23
Musarambagh
Regular—24 September 2018
24
Dilsukhnagar
Regular—24 September 2018
25
Chaitanyapuri
Regular—24 September 2018
26
Victoria Memorial
Regular—24 September 2018
27
LB Nagar
TerminalVijayawada Highway Hub24 September 2018
Geospatial Alignment

Hyderabad Metro Red Line (Line I) Route Map

Advertisement // Sponsor

Verified Partner
Loading sponsor...
Loading GIS Map Environment...

Advertisement // Sponsor

Verified Partner
Loading sponsor...
Specs sheet

Hyderabad Metro Red Line (Line I) Technical Specifications

ParameterValue
Estimated Cost14172.0
Corridor Type100% Elevated Viaduct
Primary DepotMiyapur Maintenance Depot (~100 acres)
Track GaugeStandard Gauge (1435 mm)
Total Length29 km
Opened / Est. Opening29 November 2017 (Miyapur–Ameerpet) / 24 September 2018 (Ameerpet–LB Nagar)
Corridor StatusFully Operational
Operating Timings / Hours06:00 to 23:00 (Daily from Miyapur and LB Nagar terminals)
Maximum Design Speed90 km/h (Design Speed) / 80 km/h (Maximum Operating Speed)
OperatorHMRL (100% Equity Owner) | L&TMRHL & Keolis (Operations & Maintenance)
Stations Count27 Stations
Line NumberCorridor I (Red Line)
Electrification System25kV 50Hz AC Overhead Catenary (OHE)
Chronological Milestones

Hyderabad Metro Red Line (Line I) Timeline

July 2012

Ground works for Hyderabad Metro Phase I commenced

2016

Trial runs commenced between Miyapur and SR Nagar

29 November 2017

Priority section from Miyapur to Ameerpet (13 km, 11 stations) inaugurated for commercial operations

24 September 2018

Remaining section from Ameerpet to LB Nagar (16 km, 16 stations) opened for commercial service

29 April 2026

HMRL signed the agreement to acquire 100% equity of LTMRHL. Operations shifted to state ownership from 1 May 2026

Proprietary analytics

Hyderabad Metro Red Line (Line I) Economic & Connectivity Impact

Economic Significance

According to HMRL, travel time from Miyapur to LB Nagar is covered in approximately 45 minutes by rapid transit.

Traffic Impact

Serves heavy commuter traffic along NH-65, relieving congestion across Kukatpally, Ameerpet, Punjagutta, and Dilsukhnagar.

Employment Centres Served

Connects dense residential hubs (KPHB, Kukatpally, Dilsukhnagar) directly to central commercial areas at Ameerpet, Punjagutta, and Nampally.

Intermodal Connectivity

Provides metro-to-metro transfers at Ameerpet (Blue Line) and MGBS (Green Line), along with rail connectivity at Nampally and MMTS suburban stations.

Geospatial Explorer

Hyderabad Metro Red Line (Line I) Alignment Map & GIS Explorer

Elevated / UndergroundElevated: 29 km | Underground: 0 km
Viaduct Length29 km
Tunnel Length0 km
Primary DepotMiyapur Depot (Lat: 17.498, Lon: 78.362)

Advertisement // Sponsor

Verified Partner
Loading sponsor...

Advertisement // Sponsor

Verified Partner
Loading sponsor...
Answers

Frequently Asked Questions

The Hyderabad Metro Red Line is Corridor I of the Hyderabad Metro, connecting Miyapur in the northwest with LB Nagar in the southeast. It is about 29 km long and has 27 stations, with interchange connections at Ameerpet and MG Bus Station.

Advertisement // Sponsor

Verified Partner
Loading sponsor...

Enjoy tracking infrastructure projects?

Get monthly updates whenever major Indian infrastructure projects move forward.

✓Project milestones
✓Government approvals
✓Construction progress
✓New project launches
🏛️Visit Telangana Dashboard →TS
🗺️Explore All State Dashboards →ALL
📰Read Latest Infrastructure News →LATEST
Android App Live

Indian Infraproject In Your Pocket — Full route alignments on the go, live GPS positioning & instant alerts.

Get on Google Play
Sponsored // Advertisement