The New Mumbai–Pune Greenfield Expressway is a proposed 130 km access-controlled 8-lane expressway corridor planned by NHAI to connect Chirle (Navi Mumbai / MTHL junction) directly to Pune (NH-48 ring road). Envisioned as an ultra high-speed relief route for the existing Mumbai–Pune Expressway, the alignment features extensive tunnels through the Western Ghats to deliver a flat-gradient ~1-hour transit time.
Reach thousands of decision-makers and investors searching for infrastructure projects every month.
New Mumbai-Pune Expressway DPR & Construction Status
The National Highways Authority of India (NHAI), functioning under the Ministry of Road Transport and Highways (MoRTH), has initiated planning for the New Mumbai–Pune Greenfield Expressway. On May 11, 2026, NHAI Project Implementation Unit (PIU) Pune invited open bids under Tender ID 2026_NHAI_277178_1 (Tender Ref: MHDIV-20020/288/2025-PIU Pune/302061) for Consultancy Services to prepare the Detailed Project Report (DPR) and Feasibility Report for this estimated ₹15,000 crore access-controlled corridor (estimated cost, not a sanctioned budget).
The existing 94.5 km Mumbai–Pune Expressway (Yashwantrao Chavan Expressway), operational since 2002, experiences heavy traffic volumes and recurring congestion points through Khandala Ghat and urban entry nodes.
Distinction from MSRDC Missing Link: This proposed 130 km NHAI greenfield corridor is entirely independent of MSRDC's 13.3 km Missing Link project (Khopoli to Kusgaon), which is a localized bypass on the existing 6-lane expressway. In contrast, the proposed New Greenfield Expressway is conceived as an 8-lane parallel arterial corridor designed with the objective of relieving traffic congestion on the existing corridor.
Under the scope of the DPR assignment, the alignment will undergo digital verification via the PM Gati Shakti National Master Plan Portal to ensure optimal multi-modal connectivity with the Mumbai Trans Harbour Link (Atal Setu), Jawaharlal Nehru Port (JNPA), Navi Mumbai International Airport (NMIA), the Virar-Alibaug Multi-Modal Corridor (VAMC), and the Pune Outer Ring Road.
Chowk to Shivare Expressway Route & Connectivity
The proposed 130 km greenfield corridor is currently under study across Raigad and Pune districts in Maharashtra. Under initial planning, the highway is proposed to originate near Chowk in Khalapur Taluka, Raigad District, where the Old Mumbai–Pune Highway (NH-48) intersects regional corridors. The proposed Chowk–Shivare alignment is subject to DPR finalization and official approval.
Under current planning, the project incorporates proposed connectivity via NH-548A (Pagote–Chowk corridor), allowing traffic crossing Mumbai's 21.8 km Atal Setu (MTHL) at Chirle to connect toward the proposed greenfield alignment near Chowk. In the vicinity of Chowk, it is also planned to interface with the proposed Virar-Alibaug Multi-Modal Corridor.
From Chowk, the proposed alignment traverses the foothills and plateau terrain of the Western Ghats (Sahyadri ranges), where potential engineering features such as tunnels and viaducts may be evaluated during the DPR study to address hilly gradients. The proposed southern terminus arrives at Shivare (Shivre) village near Khed Shivapur in Bhor Taluka, intersecting the under-construction Pune Outer Ring Road and connecting toward the upcoming Pune–Bengaluru Expressway. The proposed Chowk–Shivare alignment is subject to DPR finalization and official approval.
Advertisement // Sponsor
Verified PartnerNew Mumbai-Pune Greenfield Expressway Route Map
(नया मुंबई-पुणे एक्सप्रेसवे रूट मैप)The interactive GIS map displays the indicative schematic alignment and proposed anchor points between Chowk (Raigad) and Shivare near Khed Shivapur (Pune). As the project is currently in the DPR consultancy tender stage, the red dotted line illustrates the proposed schematic corridor connection. Detailed ground-truthed centerline coordinates will be updated following final statutory gazette notification by NHAI.
Advertisement // Sponsor
Verified PartnerNew Mumbai-Pune Greenfield Expressway Cost & Length
The technical specifications and alignment parameters outlined below reflect the official NHAI DPR consultancy procurement scope (Tender Ref: MHDIV-20020/288/2025-PIU Pune/302061). The project is proposed to high-speed access-controlled standards, with scope for advanced traffic management systems (ATMS), potential wildlife crossings, and modern tolling infrastructure to be detailed in the DPR.
| Parameter | Technical Details |
|---|---|
| Project Name | New Mumbai–Pune Greenfield Expressway (Atal Setu to Pune Link) |
| Total Length | Approx. 130 km (8-Lane Proposed Access-Controlled Alignment) |
| Estimated Project Cost | ₹15,000 Crore (Estimated Cost — Not Sanctioned Budget) |
| Implementing Authority | National Highways Authority of India (NHAI) — PIU Pune |
| Starting Point | Chowk, Khalapur Taluka, Raigad (Junction with NH-48 & NH-548A) |
| Ending Point | Shivare (Shivre), Bhor Taluka, Pune District (Pune Ring Road Interchange) |
| Districts Covered | Raigad, Pune (Maharashtra) |
| Major Intersecting Corridors | Mumbai Trans Harbour Link (Atal Setu), NH-548A, Pune Outer Ring Road, NH-48 |
| Current Project Phase | DPR consultancy tender stage (RFP Invited May 2026) |
| Tender Reference ID | MHDIV-20020/288/2025-PIU Pune/302061 (Tender ID: 2026_NHAI_277178_1) |
| Tolling System | Tolling system not yet officially confirmed. |
| Target Design Speed | Design speed subject to DPR confirmation. |
| Targeted Travel Time | is projected to reduce travel time to approximately 90 minutes. |
New Mumbai-Pune Expressway Completion Date
According to NHAI's Terms of Reference (TOR), the project execution framework is structured across four progressive phases:
- Stage 1 (First 90 Days): Traffic surveys (axle load surveys and 30-year forecasting), LiDAR-based preliminary topographical surveys, and multi-criteria alignment validation through the PM Gati Shakti portal.
- Stage 2 (DPR & Clearances): Geotechnical drilling, tunnel rock mechanics analysis, pavement design, and statutory environmental, forest, and CRZ clearances.
- Stage 3 (Land Acquisition): Publication of gazette notifications under Section 3A, 3D, and 3G of the National Highways Act, 1956 across villages in Raigad and Pune districts.
- Stage 4 (Civil Works & Construction): Competitive bidding on EPC / HAM / BOT (Toll) modes, with civil execution scheduled after statutory clearances.
Atal Setu (MTHL) & Pune Outer Ring Road Connectivity
The New Mumbai–Pune Greenfield Expressway proposal features multi-modal connectivity at both regional endpoints:
Northern Integration (Mumbai & Atal Setu): Rather than passing through congested urban nodes around Kalamboli and Panvel, commuters from South and Central Mumbai crossing the 21.8 km Atal Setu (MTHL) to Chirle would utilize proposed connectivity via NH-548A (Pagote–Chowk corridor) to reach the proposed greenfield expressway near Chowk.
Southern Integration (Pune Outer Ring Road): At its proposed southern terminus in Shivare (Shivre) village, the expressway is planned to connect with the under-construction Pune Outer Ring Road. This integration is intended to allow commuters bound for East Pune (Hadapsar, Wagholi, Magarpatta), West Pune (Hinjawadi IT Park, Wakad), or traveling along NH-48 toward Satara, Kolhapur, and the proposed Pune–Bengaluru Expressway to bypass Pune municipal traffic grids. The proposed Chowk–Shivare alignment is subject to DPR finalization and official approval.
Travel Time Reduction & Traffic Decongestion Impact
Under current travel conditions, travelling between Mumbai and Pune via the existing Mumbai–Pune Expressway (Yashwantrao Chavan Expressway) or Old Mumbai–Pune Highway (NH-48) frequently takes between 3 to 4.5 hours during peak weekend hours, holidays, and heavy commercial freight windows. Common pain points include toll plaza pileups, ghat bottle-necking, and entry bottlenecks around Kalamboli and Ravet.
With the New Mumbai–Pune Greenfield Expressway, the corridor is projected to reduce travel time to approximately 90 minutes. By potentially diverting long-haul freight traffic, container shipments from JNPA, and inter-city passenger traffic, this third high-speed corridor is expected to help decongest the Mumbai-Pune industrial belt, contribute to reduced logistics freight costs, and improve road safety.
Advertisement // Sponsor
Verified PartnerNew Mumbai-Pune Expressway Latest News 2026
Video Updates
Advertisement // Sponsor
Verified PartnerFrequently Asked Questions (FAQ)
Related Infrastructure Projects
Pune Mumbai Expressway
A 94.5 km 6-lane access-controlled concrete toll expressway developed by MSRDC connecting Mumbai and Pune, featuring the landmark 13.3 km Missing Link bypass.
View Project →Pune Ring Road
A premium 136.8 km outer circular ring bypass road easing logistics transit surrounding Pune metropolis.
View Project →Virar Alibaug Multimodal Corridor
A planned 8-lane expressway combining rapid transit, highways, and utility lines, connecting Virar to Alibaug to ease congestion in MMR.
View Project →Mumbai Coastal Road
A 29.2 km coastal route utilizing undersea tunnels and reclaimed land along Mumbai's western coastline.