METRO CORRIDOR DOSSIER // KOLKATA-METRO-YELLOW-LINE-UNDER-CONSTRUCTION

Kolkata Metro Line 4 (Yellow Line — Under Construction Section: Jai Hind Airport ↔ Michael Nagar)

Under Construction / Execution📏 2.06 km Under Construction Route🚉 2 Planned Underground Stations (Birati and Michael Nagar) Stations🗓 Target Opening: 2027🏢 Metro Railway, Kolkata (Owner: Indian Railways / RVNL)

Kolkata Metro Line 4 (Yellow Line - Under Construction Segment) spans 2.06 km across 2 underground stations (Birati and Michael Nagar). Extending from the operational Jai Hind (NSCBI Airport) subterranean terminal, this underground section passes through Birati to Michael Nagar, bypassing heavy surface encroachments and airport runway obstruction zones along Jessore Road.

FEATURED PARTNER
ADVERTISEMENT

Want Your Brand Featured Here?

Reach thousands of decision-makers and investors searching for infrastructure projects every month.

YOUR BRAND HEREPrime Infrastructure Placement
Kolkata Metro Line 4 (Yellow Line - Under Construction) Economics

Kolkata Metro Line 4 (Yellow Line - Under Construction) Economics

Project CostUnderground Revision Modification Cost ₹1,615 Cr
Primary BackersMinistry of Railways (Government of India)
Operator / ModelRail Vikas Nigam Limited (RVNL) Execution
Target Opening

Expected Completion Date

StatusUnder Construction / Execution
Target Opening DateTarget Opening: 2027
Station list

Kolkata Metro Line 4 (Yellow Line - Under Construction) Stations

#StationTypeInterchange / ConnectionOpened
01
Jai Hind
Underground Operational HubNSCBI Airport Terminal & Line 6 Orange Line Interchange25 August 2025
02
Birati
Underground (Under Construction)Birati Suburb & Jessore Road Junction NodeTarget 2027
03
Michael Nagar
Underground (Under Construction)Michael Nagar Terminal & Barasat Alignment ShaftTarget 2027
Geospatial Alignment

Jai Hind Airport ↔ Michael Nagar Underground Alignment Map

Advertisement // Sponsor

Verified Partner
Loading sponsor...
Loading GIS Map Environment...

Advertisement // Sponsor

Verified Partner
Loading sponsor...
Specs sheet

Kolkata Metro Line 4 (Yellow Line - Under Construction) Technical Specifications

ParameterValue
Estimated CostSanctioned Phase
Corridor TypeUnderground Cut-and-Cover Tunneling & TBM Shaft Drive
Primary DepotNoapara Metro Depot
Track GaugeBroad Gauge (1,676 mm / 5 ft 6 in)
Total Length2.06 km Under Construction Route
Opened / Est. OpeningTarget Opening: 2027
Corridor StatusUnder Construction / Execution
Peak HeadwayTarget 8 – 10 min
OperatorMetro Railway, Kolkata (Owner: Indian Railways / RVNL)
Stations Count2 Planned Underground Stations (Birati and Michael Nagar)
Daily RidershipProjected 80,000+ Daily Passengers upon Birati/Michael Nagar Extension
Line NumberLine 4 (Yellow Line)
Signalling SystemCBTC Signalling System
Rolling StockICF Standard & CRRC Dalian Broad Gauge AC Rakes
Maximum Operating Speed80 km/h Design Speed
Electrification System750V DC Third Rail
Chronological Milestones

Kolkata Metro Line 4 (Yellow Line - Under Construction) Timeline

June 2019

Railway Board sanctioned ₹1,615 Cr material modification converting Airport–Michael Nagar section underground.

2020

Airports Authority of India (AAI) shifted fuel tanks, utility buildings, and radar cables for underground tunneling.

February 2021

Prime Minister Narendra Modi approved underground cut-and-cover method to prevent eviction of local families along Jessore Road.

25 August 2025

Operational Yellow Line to Jai Hind Airport commissioned; active civil works continued towards Birati and Michael Nagar.

Target 2027

Targeted completion of underground tunneling and commissioning of Birati and Michael Nagar metro stations.

Proprietary analytics

Yellow Line Airport Extension & Northern Suburban Connectivity

Economic Significance

Provides underground high-capacity transit connecting NSCBI Airport directly to dense northern suburban residential zones at Birati and Michael Nagar.

Traffic Impact

Bypasses massive traffic gridlocks on Jessore Road and National Highway 12 (NH-12).

Employment Centres Served

Enables fast daily commute for airport staff, cargo logistics workers, and North 24 Parganas suburban residents.

Intermodal Connectivity

Provides seamless continuous single-seat ride from Birati and Michael Nagar into Noapara and Central Kolkata.

Impact on Real Estate

Sparked commercial redevelopment and residential housing demand in Birati and Michael Nagar.

Geospatial Explorer

Kolkata Metro Line 4 (Yellow Line - Under Construction) Alignment Map & GIS Explorer

Corridor Type Breakdown2.06 km Underground Tunnels (2 Stations)
Viaduct LengthN/A (Full 2.06 km section is underground)
Tunnel Length2.06 km Underground Cut-and-Cover Tunnels
River CrossingsBagjola Canal Underground Culvert Drive
Major Bridges / CrossingsN/A
Primary DepotNoapara Metro Depot

Advertisement // Sponsor

Verified Partner
Loading sponsor...

Advertisement // Sponsor

Verified Partner
Loading sponsor...
Answers

Frequently Asked Questions

The Kolkata Metro Yellow Line, or Line 4, is being extended beyond the operational Jai Hind Airport station toward Michael Nagar. The under-construction section covered by this project is the 2.06 km Jai Hind Airport–Michael Nagar section.

Advertisement // Sponsor

Verified Partner
Loading sponsor...

Enjoy tracking infrastructure projects?

Get monthly updates whenever major Indian infrastructure projects move forward.

✓Project milestones
✓Government approvals
✓Construction progress
✓New project launches
🏛️Visit Maharashtra Dashboard →MH
🗺️Explore All State Dashboards →ALL
📰Read Latest Infrastructure News →LATEST
Android App Live

Indian Infraproject In Your Pocket — Full route alignments on the go, live GPS positioning & instant alerts.

Get on Google Play
Sponsored // Advertisement