Verified PartnerNashik–Ahilyanagar Greenfield Highway Route Map, Status & Latest Updates (2026)
The Nashik–Ahilyanagar Greenfield Highway is a planned 152 km long, 6-lane access-controlled highway corridor connecting Adgaon near Nashik (NH-60) to the Ahilyanagar Bypass (km 290). Developed under NHAI BOT (Toll) mode, it forms Phase 1 of the high-speed Surat–Chennai Economic Corridor link in northern Maharashtra.
"The Indian infrastructure project 'Nashik–Ahilyanagar Greenfield Highway' has seen significant progress since its approval in May. The Cabinet approved the construction of a six-lane greenfield highway worth Rs 19,142 crore in Maharashtra, including land acquisition for a total project length of 374 km. Land acquisition processes have hit key milestones, and construction has begun. In addition, the project is moving forward under the BOT (Toll) mode, with progress on both contract status and operations remaining robust."
नाशिक–अहिल्यानगर ग्रीनफिल्ड महामार्ग
नाशिक (आडगाव) ते अहिल्यानगर बायपास दरम्यान १५२ किमी लांबीचा ६-पदरी ग्रीनफिल्ड महामार्ग एनएचएआय द्वारे विकसित केला जात आहे. हा महामार्ग नाशिक आणि अहिल्यानगर मधील प्रवासाचा वेळ निम्म्याने कमी करेल.
Want Your Brand Featured Here?
Reach thousands of decision-makers and investors searching for infrastructure projects every month.
Nashik–Ahilyanagar Greenfield Highway Route Map & Alignment
View and download the latest Nashik–Ahilyanagar Greenfield Highway route map showing the project alignment, major junctions, districts covered and connectivity corridors.
Advertisement // Sponsor
Verified PartnerAdvertisement // Sponsor
Verified PartnerNashik–Ahilyanagar Greenfield Highway Technical Specs & Project Parameters
| Parameter | Technical Specification |
|---|---|
| Project Name | Nashik–Ahilyanagar Greenfield Highway (Ahilyanagar Bypass Package I) |
| Total Length | 152 km (6-Lane Access-Controlled Greenfield Highway) |
| Current Status | Tendering & Land Acquisition Stage |
| Estimated Cost | ₹7,596.33 Crore (NHAI Tender Value) |
| Development Model | BOT (Toll) — Item Rate Tender under NHAI |
| Target Completion | 1,095 Days Construction Period |
| Corridor End Point | Ahilyanagar (km 290.000) |
| Corridor Start Point | Junction with NH-60 at Adgaon, Nashik (km 138.000) |
| Implementing Authority | NHAI / State Highway Authority |
Corridor Alignment & Engineering Features
Corridor Alignment & Chainage Specs
The greenfield alignment initiates at the junction with NH-60 at Adgaon in Nashik (km 138.000) and traverses south-eastwards across Nashik and Ahilyanagar (Ahmednagar) districts, bypassing congested urban stretches before integrating at Ahilyanagar (km 290.000). The approved Nashik–Solapur–Akkalkot Greenfield Corridor features a design speed of 100 km/h, with an expected average vehicular speed of about 60 km/h.
Union Cabinet Approval & Strategic Impact
Sanctioned by the Union Cabinet / CCEA in December 2025 as part of the 374-km Nashik–Solapur–Akkalkot Greenfield Corridor (aggregate cost ₹19,142 crore), the overall Nashik–Akkalkot corridor is expected to reduce travel time from about 31 hours to about 17 hours, unlocking high-speed industrial and agricultural mobility between North and South Maharashtra.
NHAI Tender & BOT Scope
NHAI issued open competitive bids under Tender ID 2026_NHAI_277028_1 (Ref: NHAI/MH/ Nashik-Ahilyanagar/ PkgI) for 6-lane access-controlled greenfield highway construction with an NHAI tender value of ₹7,596.33 crore and a 1,095-day period of work. The Package-I scope operates within a BOT (Toll) framework, with bids scheduled to close on 30 September 2026 and technical bid opening on 1 October 2026.
Broader Connectivity & Industrial Hubs
As the Nashik–Ahilyanagar section of the 374-km corridor, this greenfield highway establishes rapid access between the major manufacturing and agro-processing clusters of Nashik, Sinnar, and the Ahilyanagar district, seamlessly linking with the southern Package II alignment toward Solapur and Akkalkot.
Advertisement // Sponsor
Verified PartnerLatest Nashik–Ahilyanagar Highway News
Video Updates
Nashik–Ahilyanagar Highway Timeline & Milestones
Cabinet / CCEA Sanction
The Cabinet Committee on Economic Affairs (CCEA) approved the 374-km Nashik–Solapur–Akkalkot 6-lane greenfield economic corridor at an estimated cost of ₹19,142 crore.
NHAI Package I Tender Issued
NHAI issued open bids under Tender ID 2026_NHAI_277028_1 (Ref: NHAI/MH/ Nashik-Ahilyanagar/ PkgI) on 9 May 2026 for construction of the 6-lane greenfield highway from Adgaon/Nashik (km 138.000) to Ahilyanagar (km 290.000) with a ₹7,596.33 crore tender value and 1,095-day work period.
Bid Submission Deadline
Scheduled closing deadline for submission of technical and commercial bids under the active NHAI Package I tender.
Technical Bid Opening
Scheduled opening of technical bids submitted for the Nashik–Ahilyanagar 6-lane greenfield highway contract.
Advertisement // Sponsor
Verified PartnerNashik–Ahilyanagar Greenfield Highway FAQs
The Nashik–Ahilyanagar Highway is a 152-km, 6-lane access-controlled greenfield highway from Adgaon at km 138.000 to Ahilyanagar at km 290.000 under Ahilyanagar Bypass Package I.
The route starts at the NH-60 junction at Adgaon in Nashik and extends to Ahilyanagar, forming part of the 374-km Nashik–Solapur–Akkalkot greenfield corridor.
The Ahilyanagar Bypass Package I section is approximately 152 km, covering chainage km 138.000 to km 290.000.
The alignment runs from Adgaon near Nashik toward Ahilyanagar and forms the Nashik–Ahilyanagar section of the approved Nashik–Solapur–Akkalkot greenfield corridor.
The NHAI tender value for Ahilyanagar Bypass Package I is ₹7,596.33 crore.
No. The Package I project is currently at the tendering stage, with bids scheduled to close on 30 September 2026.
NHAI has invited bids for the 6-lane access-controlled greenfield highway, with technical bid opening scheduled for 1 October 2026.
The NHAI tender ID is 2026_NHAI_277028_1, covering the Adgaon km 138.000 to Ahilyanagar km 290.000 section.
The project is being developed by the National Highways Authority of India (NHAI) under BOT (Toll) mode.
Yes. Ahilyanagar is the current official name of Ahmednagar district, so Nashik–Ahmednagar Highway is an alternate search term for the Nashik–Ahilyanagar section.
The latest major update is that NHAI's Package I tender remains active, with the bid submission deadline set for 30 September 2026.
The NHAI tender specifies a period of work of 1,095 days.
Related Infrastructure Projects
Ahilyanagar–Hasapur Greenfield Highway
A 222 km 6-lane access-controlled greenfield highway (Ahilyanagar Bypass Pkg II, ₹9,030.38 Cr BOT Toll) linking Ahilyanagar and Solapur/Akkalkot, part of the 374-km Nashik–Solapur–Akkalkot Economic Corridor.
View Project →Pune Sambhaji Nagar Expressway
An access-controlled greenfield expressway connecting Pune and Chhatrapati Sambhaji Nagar, linking two major industrial zones in Maharashtra.
View Project →Surat Chennai Expressway
A massive greenfield and brownfield economic corridor linking Surat in Gujarat to Chennai in Tamil Nadu, passing through Maharashtra, Karnataka, Telangana, and Andhra Pradesh.
View Project →Hadapsar to Yewat Elevated Highway
A 31.5 km 6-lane elevated road + 6-lane at-grade road capacity enhancement corridor along NH-65 in Pune district with a ₹5,262 crore sanctioned cost (older MSIDC page listed ₹4,258 crore) under MSIDC / Government of Maharashtra.
View Project →Samruddhi Vadhvan Expressway
A proposed 104 km greenfield expressway connecting the Samruddhi Mahamarg with the upcoming Vadhvan Mega Port in Palghar, Maharashtra.