Verified PartnerAhilyanagar–Hasapur Greenfield Highway Route Map, Status & Latest Updates (2026)
The Ahilyanagar–Hasapur Greenfield Highway (NH-160G) is an upcoming access-controlled highway corridor developed by NHAI connecting Ahilyanagar (Ahmednagar) with Hasapur in central Maharashtra. Engineered to accelerate agrarian and industrial freight between Western Maharashtra and Marathwada, statutory land acquisition proceedings are actively underway.
"The Ahilyanagar–Hasapur Greenfield Highway is an access-controlled 6-lane greenfield highway corridor spanning ~222 km from Ahilyanagar (km 290.000) to Hasapur (km 512.000). Tendered by NHAI under BOT (Toll) mode at ₹9,030.38 crore (Ahilyanagar Bypass Package II), it forms a core section of the 374-km Nashik–Solapur–Akkalkot Economic Corridor."
अहिल्यानगर–हसापूर ग्रीनफील्ड महामार्ग (NH-160G)
अहिल्यानगर ते हसापूर दरम्यान भारतीय राष्ट्रीय राजमार्ग प्राधिकरण (NHAI) द्वारे 6-लेन ग्रीनफील्ड महामार्ग विकसित केला जात आहे. हा महामार्ग पश्चिम महाराष्ट्र आणि मराठवाड्यादरम्यान जलद मालवाहतूक सुलभ करेल.
Want Your Brand Featured Here?
Reach thousands of decision-makers and investors searching for infrastructure projects every month.
Ahilyanagar–Hasapur Greenfield Highway Route Map & Alignment
View and download the latest Ahilyanagar–Hasapur Greenfield Highway route map showing the project alignment, major junctions, districts covered and connectivity corridors.
Advertisement // Sponsor
Verified PartnerAdvertisement // Sponsor
Verified PartnerAhilyanagar–Hasapur Greenfield Highway Technical Specs & Project Parameters
| Parameter | Technical Specification |
|---|---|
| Project Name | Ahilyanagar–Hasapur Greenfield Highway (Ahilyanagar Bypass Package II) |
| Total Length | 222 km (6-Lane Access-Controlled Greenfield Highway) |
| Current Status | Tendering & Land Acquisition Stage |
| Estimated Cost | ₹9,030.38 Crore (NHAI Tender Value) |
| Development Model | BOT (Toll) — Item Rate Tender under NHAI |
| Target Completion | 1,095 Days Construction Period |
| Corridor End Point | Hasapur / Akkalkot (km 512.000 / Solapur District) |
| Corridor Start Point | Ahilyanagar (km 290.000 / Ahmednagar District) |
| Implementing Authority | NHAI / State Highway Authority |
Corridor Alignment & Engineering Features
Corridor Alignment & Chainage Specs
The greenfield alignment initiates at Ahilyanagar (km 290.000) in Maharashtra and traverses south-eastwards across Ahilyanagar, Beed, and Solapur districts before reaching Hasapur (km 512.000) in the Akkalkot region near the Maharashtra–Karnataka border. The approved Nashik–Solapur–Akkalkot corridor has a design speed of 100 km/h, with an expected average vehicular speed of about 60 km/h.
Union Cabinet Approval & Corridor Impact
Sanctioned by the Union Cabinet / CCEA in December 2025 as part of the 374-km Nashik–Solapur–Akkalkot 6-Lane Greenfield Corridor (aggregate cost ₹19,142 crore), the overall Nashik–Akkalkot corridor is expected to reduce travel time from about 31 hours to about 17 hours, boosting inter-regional transit and logistics across Maharashtra.
NHAI Tender & BOT Scope
NHAI invited open bids under Tender ID 2026_NHAI_277031_1 for 6-lane access-controlled greenfield highway construction with an NHAI tender value of ₹9,030.38 crore and a 1,095-day work period. As part of the Package-II BOT scope, the concessionaire is also entrusted with Operation and Maintenance (O&M) responsibilities across designated feeder stretches. Bids are scheduled to close on 30 September 2026, with technical bid opening on 1 October 2026.
Broader Connectivity & Regional Role
As the core 222-km segment of the 374-km Nashik–Ahilyanagar–Solapur–Akkalkot corridor, the project connects key agricultural and industrial districts across Western and Central Maharashtra towards Solapur and Akkalkot.
Advertisement // Sponsor
Verified PartnerLatest Ahilyanagar–Hasapur Highway News
Video Updates
Ahilyanagar–Hasapur Highway Timeline & Milestones
Cabinet / CCEA Sanction
The Cabinet Committee on Economic Affairs (CCEA) approved the 374-km Nashik–Solapur–Akkalkot 6-lane greenfield economic corridor at an estimated cost of ₹19,142 crore.
NHAI Package II Tender
NHAI invited bids under Tender ID 2026_NHAI_277031_1 for construction of the 6-lane greenfield highway from Ahilyanagar (km 290.000) to Hasapur (km 512.000) with a ₹9,030.38 crore tender value and 1,095-day work period.
Bid Submission Deadline
Scheduled closing deadline for submission of bids under the active NHAI Package II tender.
Technical Bid Opening
Scheduled opening of technical bids submitted for the Ahilyanagar–Hasapur 6-lane greenfield highway contract.
Advertisement // Sponsor
Verified PartnerAhilyanagar–Hasapur Greenfield Highway FAQs
The Ahilyanagar–Hasapur Highway is a 6-lane access-controlled greenfield highway from Ahilyanagar at km 290.000 to Hasapur at km 512.000 under Ahilyanagar Bypass Package II.
The project runs from Ahilyanagar at km 290.000 to Hasapur at km 512.000 in Maharashtra and forms part of the Nashik–Solapur–Akkalkot greenfield corridor.
The Ahilyanagar–Hasapur Package II stretch is approximately 222 km, based on the chainage from km 290.000 to km 512.000.
The alignment forms the central section of the 374-km Nashik–Solapur–Akkalkot 6-lane greenfield corridor, connecting the Ahilyanagar region toward Solapur and Akkalkot.
The NHAI tender value for Ahilyanagar Bypass Package II is ₹9,030.38 crore.
No. The Package II project is currently in the tendering stage, with bids scheduled to close on 30 September 2026.
NHAI has invited bids for construction of the 6-lane greenfield highway. The current tender is active and scheduled for bid opening on 1 October 2026.
NHAI Tender ID 2026_NHAI_277031_1 covers construction of the 6-lane access-controlled greenfield highway from Ahilyanagar km 290.000 to Hasapur km 512.000.
The project is being developed by the National Highways Authority of India (NHAI).
Yes. It forms part of the 374-km Nashik–Solapur–Akkalkot 6-lane greenfield access-controlled corridor approved by the Union Cabinet.
The latest major update is that the NHAI Package II tender remains active, with the bid submission deadline extended to 30 September 2026.
The approved Nashik–Solapur–Akkalkot corridor has a design speed of 100 km/h, with an expected average vehicular speed of about 60 km/h.
Related Infrastructure Projects
Nashik–Ahilyanagar Greenfield Highway
A 152 km 6-lane access-controlled greenfield highway (Ahilyanagar Bypass Pkg I, ₹7,596.33 Cr NHAI tender value) linking Nashik and Ahilyanagar, part of the 374-km Nashik–Solapur–Akkalkot Economic Corridor.
View Project →Pune Sambhaji Nagar Expressway
An access-controlled greenfield expressway connecting Pune and Chhatrapati Sambhaji Nagar, linking two major industrial zones in Maharashtra.
View Project →Surat Chennai Expressway
A massive greenfield and brownfield economic corridor linking Surat in Gujarat to Chennai in Tamil Nadu, passing through Maharashtra, Karnataka, Telangana, and Andhra Pradesh.
View Project →Hadapsar to Yewat Elevated Highway
A 31.5 km 6-lane elevated road + 6-lane at-grade road capacity enhancement corridor along NH-65 in Pune district with a ₹5,262 crore sanctioned cost (older MSIDC page listed ₹4,258 crore) under MSIDC / Government of Maharashtra.
View Project →Samruddhi Vadhvan Expressway
A proposed 104 km greenfield expressway connecting the Samruddhi Mahamarg with the upcoming Vadhvan Mega Port in Palghar, Maharashtra.