Bengaluru–Chennai Expressway (NE-7) Route Map, Toll Rates, Status & Latest Updates (2026)

(बेंगलुरु चेन्नई एक्सप्रेसवे)

National Expressway 7 (NE-7) • Hoskote to Sriperumbudur Expressway

The Bengaluru Chennai Expressway (designated National Expressway 7 / NE-7 and also known as the Bangalore Chennai Expressway or Chennai Bangalore Expressway) is India's premier 261.7 km (262 km) four-lane access-controlled greenfield highway connecting Hoskote near Bengaluru to Sriperumbudur near Chennai across Karnataka (71.7 km), Andhra Pradesh (85.0 km), and Tamil Nadu (105.0 km), engineered to cut intercity transit time from 5–6 hours to under 3 hours.

Quick Answers & Key FactsAudited October 2026
What is the Bengaluru Chennai Expressway?
The Bengaluru–Chennai Expressway (NE-7) is a 261.7 km (262 km), 4-lane access-controlled greenfield expressway developed by NHAI under Bharatmala Pariyojana connecting Hoskote (Bengaluru) to Sriperumbudur (Chennai) with a design speed of 120 km/h.
Is the Bengaluru Chennai Expressway open?
Yes, the expressway is partially open to vehicular traffic. A continuous 96.7 km dual-carriageway stretch between Hoskote (Karnataka) and Byreddipalli (Andhra Pradesh) is fully operational with active FASTag electronic toll collection.
How much of the expressway is operational?
Approximately 96.7 km is operational, comprising all 71.7 km of Karnataka Phase 1 (Hoskote to Bethamangala) and ~25.0 km of Andhra Pradesh Phase 2 Package 1 (Bethamangala to Byreddipalli).
When will the Bengaluru Chennai Expressway be completed?
Full-corridor commissioning is realistically projected for 2027–2028. While balance AP and TN sections are in advanced execution, NHAI re-tendered Tamil Nadu Package 3 (Arakkonam–Kancheepuram, ₹633.12 Cr) under an 18-month EPC contract following contractor termination.
What is the expressway route?
The 262 km alignment traverses Hoskote → Malur → Bangarapet → Bethamangala (Karnataka) → Byreddipalli → Palamaner → Bangarupalem → Gudipala / Chittoor (Andhra Pradesh) → Walajahpet → Arakkonam → Kancheepuram → Sriperumbudur (Tamil Nadu), intersecting the Bengaluru Satellite Town Ring Road (STRR) and Chittoor–Thatchur Expressway (NH-716B).
Project Status Update: Partially Operational (~96.7 km Open; Full Corridor Date to be Officially Confirmed)A continuous 96.7 km stretch from Hoskote (Karnataka) through Bethamangala up to Byreddipalli (Andhra Pradesh) is completed and open to traffic. While balance AP sections and Tamil Nadu Packages 1, 2, and 4 are advancing in civil execution, NHAI's contract termination and fresh 18-month EPC re-tendering of Package 3 (Arakkonam–Kancheepuram, ₹633.12 Cr) means full end-to-end corridor commissioning is yet to be officially confirmed, shifting realistic completion to 2027–2028.
Strategic Maritime & Industrial IntegrationDirect interchange connectivity near Chittoor with the under-construction Chittoor–Thatchur Expressway (NH-716B) provides seamless port connectivity to Kamarajar (Ennore) and Kattupalli ports, alongside linkages to the upcoming Parandur International Greenfield Airport and Chennai Peripheral Ring Road (CPRR).
हिंदी में:
बेंगलुरु चेन्नई एक्सप्रेसवे (NE-7) भारतीय राष्ट्रीय राजमार्ग प्राधिकरण (NHAI) द्वारा विकसित 261.7 किमी लंबा ग्रीनफील्ड एक्सप्रेसवे है जो कर्नाटक (71.7 किमी), आंध्र प्रदेश (85 किमी) और तमिलनाडु (105 किमी) को जोड़ता है। वर्तमान में होसकोटे से बायरेड्डीपल्ली तक लगभग 96.7 किमी का हिस्सा चालू है। तमिलनाडु पैकेज 3 के 18 महीने के पुनर्निविदा के चलते पूर्ण कॉरिडोर खुलने की तारीख अभी आधिकारिक रूप से घोषित होना बाकी है।
FEATURED PARTNER
ADVERTISEMENT

Want Your Brand Featured Here?

Reach thousands of decision-makers and investors searching for infrastructure projects every month.

YOUR BRAND HEREPrime Infrastructure Placement
Total Length262 km
Estimated Cost₹17,930 Cr
Implementing AgencyNHAI
Current Status
Partially Open(~96.7 km Operational)
Completion Target2027–2028 (Expected)

Bengaluru–Chennai Expressway Latest Update 2026

Recent progress across the 261.7 km Bengaluru–Chennai Expressway (National Expressway 7 / NE-7) demonstrates critical milestone achievements alongside key contract restructuring, transforming southern India's primary economic corridor. Developed under the Bharatmala Pariyojana program by the National Highways Authority of India (NHAI), this high-speed arterial connects seamlessly with other key mega-projects including the Bengaluru Satellite Town Ring Road (STRR), the upcoming Pune–Bengaluru Expressway, and the Bengaluru–Vijayawada Expressway.

In Karnataka, the entire 71.7 km Phase 1 stretch—comprising Packages 1, 2, and 3 from Hoskote through Malur and Bangarapet to Bethamangala—is 100% completed and open for vehicular traffic with operational FASTag tolling. Executed by Dilip Buildcon and KCC Buildcon with rigid 4-lane cement-concrete pavement, it has already shortened transit times between Bengaluru's eastern tech corridor and Kolar district.

In Andhra Pradesh, Phase 2 spanning approximately 85.0 km across Chittoor district has achieved a major milestone: Package 1 from Bethamangala up to Byreddipalli (~25.0 km) is open to traffic, extending the continuous operational length from Hoskote to approximately 96.7 km. The remaining two packages (Baireddipalle to Bangarupalem, 31.0 km, and Bangarupalem to Gudipala, 29.0 km) have attained 89% to 91% physical progress across major structures, grade separators, and mainline bituminous paving.

In Tamil Nadu, Phase 3 spans 105.0 km from the Andhra Pradesh border near Gudipala to Sriperumbudur. While Packages 1, 2, and 4 are advancing in civil execution (~79% to 85%), progress on Package 3 (Arakkonam to Kancheepuram, 25.5 km, Km 204.500 to Km 230.000) was disrupted after work stalled in May 2025 at approximately 53.56% physical progress (11.33 km completed) due to the financial default of the original concessionaire.

Authoritative Tender Update (Corrigendum 3 Issued 27 October 2026)Following contract termination and clearance from the Madras High Court, NHAI invited fresh EPC tenders for the balance works of Tamil Nadu Package 3 (Tender ID: 2026_NHAI_289557_1 / Ref: NHAI/11029/22c/2019/ PIU Kanchee/E 211360) valued at ₹633.12 crore with an 18-month execution period. On 27 October 2026, NHAI issued official Corrigendum 3 extending the bid submission closing date to 10 November 2026 (technical opening on 11 November 2026). Given this 18-month civil window, full end-to-end corridor commissioning between Bengaluru and Chennai has realistically shifted to 2027–2028.

Bengaluru–Chennai Expressway Route

The greenfield corridor spans 261.7 km (officially rounded to 262 km) across three southern states—Karnataka (71.7 km), Andhra Pradesh (85.0 km), and Tamil Nadu (105.0 km). The alignment starts at Hoskote in Bengaluru Rural district, connecting directly with the Bengaluru Satellite Town Ring Road (STRR / NH-648) and Old Madras Road (NH-75), and terminates at Sriperumbudur on the western outskirts of Chennai, interfacing directly with NH-48 and the Chennai Peripheral Ring Road (CPRR).

Unlike the existing congested National Highway 48 (which runs through Hosur, Krishnagiri, Vaniyambadi, Ambur, and Ranipet over a circuitous 340+ km route), the NE-7 alignment takes a shorter, direct greenfield path north of the Eastern Ghat foothills, completely bypassing crowded urban bottlenecks.

States Covered & Route Alignment
Karnataka (71.7 km)Hoskote (Start / STRR Interchange), Malur, Bangarapet, Bethamangala
Andhra Pradesh (85.0 km)Byreddipalli, Palamaner, Bangarupalem, Gudipala / Chittoor (NH-716B Spur)
Tamil Nadu (105.0 km)Walajahpet, Arakkonam, Kancheepuram, Sriperumbudur (Terminus / CPRR Interface)

Advertisement // Sponsor

Verified Partner
Loading sponsor...
Interactive GIS Corridor Path

Bengaluru Chennai Expressway Route Map

The interactive GIS map showcases the physical alignment, real-time package statuses, and coordinate path of the Bengaluru–Chennai Expressway (बेंगलुरु चेन्नई एक्सप्रेसवे रूट मैप). Users can view the exact geographic coordinate paths across Hoskote, Kolar, Chittoor, Ranipet, Kanchipuram, and Sriperumbudur, bypassing traditional congested state highways. This mapping interface displays contractor allocations, construction percentages, and package breakdowns for all 10 project stretches.

Loading GIS Map Environment...

Advertisement // Sponsor

Verified Partner
Loading sponsor...
Live Alignment Parameters

Bengaluru Chennai Expressway Opening Date & Current Status

The corridor is designed as an access-controlled expressway with an initial 4-lane cross-section (expandable up to 8 lanes) within a wide 90-meter Right of Way (RoW). Approximately 96.7 km is currently operational (Karnataka Phase 1 and AP Package 1 to Byreddipalli), while balance packages across Andhra Pradesh and Tamil Nadu are progressing through active civil execution and re-tendered balance works.

ParameterTechnical Details
Project NameBengaluru–Chennai Expressway (National Expressway 7 / NE-7)
Total Length261.7 km (officially 262 km; 4-lane Access-Controlled, expandable to 8 lanes with 90m RoW)
Current Operational Length~96.7 km (Hoskote to Byreddipalli open to traffic)
Estimated Cost₹17,930 Cr (Bharatmala Pariyojana / National Expressway program)
Implementing AuthorityNational Highways Authority of India (NHAI) / MoRTH
States CoveredKarnataka (71.7 km), Andhra Pradesh (85.0 km), Tamil Nadu (105.0 km)
Major Connected SpursChittoor–Thatchur Expressway (NH-716B) to Ennore & Kattupalli Ports, Bengaluru STRR (NH-648), CPRR & Parandur Airport Link
Current PhasePartially Operational (96.7 km open; balance AP & TN packages in progress / re-tendered)
Start DateNovember 2021 (Civil construction kicked off in Karnataka)
Expected Completion DateFull corridor completion date is yet to be officially confirmed (18-month Package 3 balance works underway; 2027–2028 expected)
Total Construction Packages10 packages active across 3 execution phases
Notified Speed Limits120 km/h (Cars/LMVs) | 100 km/h (Buses) | 80 km/h (Trucks) under MoRTH Notification S.O. 1522(E)
Notified Toll Rates (Operational Section)Closed tolling: ₹150 for cars (Hoskote–Bethamangala single), ₹225 (same-day return), ₹4,955 (monthly pass)
Official NHAI Gazetted Tariff

Bengaluru Chennai Expressway Toll Charges 2026

FASTag Closed Distance-Based Tolling System

Tolling operations across the open stretches of the Bengaluru–Chennai Expressway (NE-7) follow a modern distance-based closed tolling model via computerized FASTag Electronic Toll Collection (ETC). Vehicles are recorded at electronic entry gantries (such as Hoskote, Malur, Bangarapet, and Bethamangala) and charged only for the exact distance travelled upon exiting the expressway corridor.

Below is the officially notified NHAI user fee schedule currently applicable for the operational 71.7 km Karnataka stretch between Hoskote and Bethamangala:

Toll Plazas

Operational Closed-Loop Toll Plazas (Karnataka & Andhra Pradesh)

5 Active Plazas
#Plaza NameChainageStateLocation & Closed-Loop Interchanges
1Hedaginabele Toll PlazaKM 0.000KarnatakaLocated near Hoskote, this marks the western entry and exit point of the expressway.
2Agrahara Toll PlazaKM 27.500KarnatakaPositioned along the Hoskote–Malur route for vehicles entering or exiting near Malur.
3Krishnavaram / Krishnarajapura Toll PlazaKM 55.000KarnatakaSituated near BEML Nagar in Kolar Gold Fields (KGF) serving local logistics.
4Sundarapalya Toll PlazaKM 71.700KarnatakaLocated in KGF taluk near Bethamangala, marking the completion of the 71.7-km Karnataka section.
5Baireddypalle Toll PlazaKM 96.700Andhra PradeshCovers the operational 25-km Andhra Pradesh stretch extending from the Karnataka border to Baireddypalle.
On the operational stretches of the Bengaluru–Chennai Expressway (NE-7), the effective per-kilometer toll rate for cars and light vehicles is ₹2.03 to ₹2.11 per km. Because the expressway uses a closed-loop, distance-based tolling system, you are scanned at entry (₹0 scan) and charged based on the distance traveled when you exit. Additional toll plazas will open along the eastern corridor in Tamil Nadu toward Sriperumbudur once civil works conclude.
Interactive Toll Tariff

Calculate Exact Toll Rates & Journey Price

Check single trip, return journey discounts, monthly pass tariffs, and per km pricing for Car, LCV, Bus, Truck, and Multi-Axle vehicles across all verified plazas on the Toll Calculator.

Calculate Toll Price →
Notified Speed Limits (MoRTH S.O. 1522(E))
  • M1 Passenger Vehicles (Cars / SUVs):120 km/h
  • M2 & M3 Passenger Carriers (Buses):100 km/h
  • N Category Freight Haulers (Trucks):80 km/h
Prohibited Vehicle Categories

To guarantee corridor safety at high design speeds, NHAI strictly prohibits two-wheelers (motorcycles, scooters), three-wheelers (auto-rickshaws, e-rickshaws), non-motorized vehicles, and agricultural tractors from entering the mainline expressway carriageway. Dedicated service roads serve local village traffic.

Civil Contracts & Execution Audit

Bengaluru Chennai Expressway Package-Wise Construction Progress

10 Packages Across 3 States (261.7 km Corridor)

The Bengaluru–Chennai Expressway is divided into 10 civil construction packages across three execution phases. Phase 1 in Karnataka (Packages 1–3, 71.7 km) is 100% completed and operational with computerized FASTag tolling. Phase 2 in Andhra Pradesh (Packages 1–3, 85.05 km) has achieved operational status up to Byreddipalli on Package 1, extending the continuous open corridor to ~96.7 km, with Packages 2 and 3 at 89%–91% physical progress. Phase 3 in Tamil Nadu (Packages 1–4, 106.1 km) has Packages 1, 2, and 4 under active civil execution (79%–85%), while Package 3 (Arakkonam–Kancheepuram, 25.5 km) was terminated following contractor financial default and re-tendered by NHAI under EPC mode for ₹633.12 Cr (Corrigendum 3 issued 27 October 2026, bid submission extended to 10 November 2026).

Phase 1: Karnataka71.7 km (100% Operational)

Packages 1, 2 & 3 fully completed by Dilip Buildcon and KCC Buildcon; tolling active from Hoskote to Bethamangala.

✓ 3 of 3 Packages Open
Phase 2: Andhra Pradesh85.05 km (~92% Avg Progress)

Package 1 open to Byreddipalli (~25 km); Packages 2 & 3 in advanced stages across Chittoor district with NH-716B interchange.

~25 km Operational | 2 In Progress
Phase 3: Tamil Nadu106.1 km (~75% Avg Progress)

Packages 1, 2, 4 progressing smoothly. Package 3 re-tendered under fresh ₹633.12 Cr EPC contract (18-month execution period).

3 In Progress | 1 Re-tendered
Pkg CodeState & StretchLengthContractorProgressOperational StatusTarget
Phase 1: Karnataka (Total Length: 71.7 km — 100% Operational)
BCE-KA-PKG1Hoskote to MalurKm 0.000 to Km 26.400 (STRR Interchange)26.4 km(27.1 km with STRR links)Dilip Buildcon Ltd.100%Fully OperationalOpen to Traffic
BCE-KA-PKG2Malur to BangarapetKm 26.400 to Km 53.50027.1 kmDilip Buildcon Ltd.100%Fully OperationalOpen to Traffic
BCE-KA-PKG3Bangarapet to BethamangalaKm 53.500 to Km 71.000 (AP Border)17.5 km(18.2 km incl. border link)KCC Buildcon Pvt. Ltd.100%Fully OperationalOpen to Traffic
Phase 2: Andhra Pradesh (Total Length: 85.05 km — Chittoor District)
BCE-AP-PKG1Bethamangala to Byreddipalli25.05 kmMontecarlo Limited (MCL)96%Open (~25 km)Fully Operational
BCE-AP-PKG2Baireddipalle to Bangarupalem31.0 kmApco Infratech Pvt. Ltd.89%Under ConstructionMid 2026
BCE-AP-PKG3Bangarupalem to Gudipala29.0 kmDilip Buildcon Ltd.91%Under ConstructionMid 2026
Phase 3: Tamil Nadu (Total Length: 106.1 km — Ranipet, Vellore & Kanchipuram Districts)
BCE-TN-PKG1Gudipala to Walajahpet24.0 kmMontecarlo Limited81%Under Construction2026–2027
BCE-TN-PKG2Walajahpet to Arakkonam24.5 kmKCC Buildcon Pvt. Ltd.79%Under Construction2026–2027
BCE-TN-PKG3Arakkonam to KancheepuramKm 204.500 to Km 230.000 (Corrigendum 3: 27 Oct 2026)25.5 kmFresh NHAI EPC Tender₹633.12 Cr / 18-month balance works (Bid close: 10 Nov 2026)54%11.33 km pavedRe-tendered2027–2028
BCE-TN-PKG4Kancheepuram to SriperumbudurKm 230.000 to Km 261.700 (CPRR Junction)31.7 km(32.1 km DPR scope)Chetak Enterprises / RCC Infra JV85%Under Construction2026–2027

Bengaluru–Chennai Expressway Completion Date

Project Status Update: Full Corridor Completion Date is Yet to be Officially ConfirmedWhile the Karnataka segment (71.7 km from Hoskote to Bethamangala) and Andhra Pradesh Package 1 are operational (running continuously for 96.7 km to Byreddipalli), full end-to-end corridor commissioning has shifted. Following contract termination of the concessionaire on Package 3 in Tamil Nadu (Arakkonam–Kancheepuram), NHAI issued a fresh EPC tender with an 18-month construction period, realistically shifting complete corridor commissioning to 2027–2028.
Phased Commissioning RoadmapNHAI is pursuing sequential operationalization: with 96.7 km already open between Hoskote and Byreddipalli, the remaining ~58 km in Andhra Pradesh (Bangarupalem and Gudipala) is targeting substantial completion, followed by Tamil Nadu Packages 1, 2, and 4. The final bottleneck remains Package 3, where balance bridge and pavement construction will dictate end-to-end commissioning.

The completion schedule of the Bengaluru–Chennai Expressway reflects a phased commissioning model. Phase 1 in Karnataka (71.7 km) is already open to public traffic. In Andhra Pradesh (Phase 2), all three packages spanning 85.0 km from Bethamangala to Gudipala are substantially advanced, with the stretch up to Byreddipalli already commissioned for traffic.

In Tamil Nadu (Phase 3), the critical path for completion centers around Package 3 (Arakkonam to Kancheepuram, 25.5 km), which faced execution delays and stoppage under the original concessionaire, D.P. Jain & Co. After contract termination, NHAI floated fresh EPC tenders valued at ₹633.12 crore with an 18-month construction period to execute remaining structures including 9 major bridges, 1 railway overbridge, and multiple underpasses. Full corridor completion date is yet to be officially confirmed, with completion realistically anticipated in 2027–2028.

Chittoor–Thatchur Spur, Port Connectivity & Logistics Impact

A major highlight of the Bengaluru–Chennai Expressway is its strategic multi-modal freight connectivity. Near Chittoor in Andhra Pradesh, the alignment intersects directly with the 116 km under-construction Chittoor–Thatchur Greenfield Expressway (NH-716B), which also connects towards the Surat–Chennai Expressway economic corridor.

This dedicated freight spur allows heavy container trailers and commercial logistics fleets travelling between Bengaluru's manufacturing clusters (Peenya, Hoskote, Bidadi, Narasapura) to bypass Chennai's congested inner ring roads completely. Cargo trucks can proceed directly toward Kamarajar Port (Ennore) and Kattupalli Port in North Chennai. Additionally, the eastern terminus at Sriperumbudur links directly into the auto-manufacturing corridor of Sriperumbudur-Oragadam and the proposed Parandur International Greenfield Airport near Kanchipuram.

Bangalore to Chennai Expressway Travel Time & Distance

Travel time reduction between Karnataka and Tamil Nadu is the primary socioeconomic benefit of the project. Currently, road commuters between Bengaluru and Chennai rely on NH-48 (via Hosur, Krishnagiri, Vellore, and Ranipet) or NH-75 (via Kolar, Chittoor, and Ranipet), covering between 330 km and 350 km. Due to heavy traffic congestion, industrial freight density, and multiple toll plazas, this journey typically requires 5 to 6 hours by car and over 7 to 8 hours by bus or truck.

Once the 262 km Bengaluru–Chennai Expressway is fully commissioned, travel time will drop to approximately 2.5 to 3 hours at a continuous design speed of 120 km/h. By cutting nearly 80 km off the travel distance and eliminating all urban bottlenecks, the corridor will slash fuel consumption, lower logistics transport costs by over 20%, and facilitate same-day turnarounds for commercial fleets.

Advertisement // Sponsor

Verified Partner
Loading sponsor...
Timeline

Bengaluru Chennai Expressway Latest News

Verified project updates from news sources and official announcements
Video Coverage

Video Updates

Latest drone footage, progress reports, and ground coverage

Advertisement // Sponsor

Verified Partner
Loading sponsor...
Q&A

Frequently Asked Questions

Related Infrastructure Projects

Advertisement // Sponsor

Verified Partner
Loading sponsor...

Enjoy tracking infrastructure projects?

Get monthly updates whenever major Indian infrastructure projects move forward.

✓Project milestones
✓Government approvals
✓Construction progress
✓New project launches
🏛️Visit Karnataka Dashboard →KA
🗺️Explore All State Dashboards →ALL
📰Read Latest Infrastructure News →LATEST
Android App Live

Indian Infraproject In Your Pocket — Full route alignments on the go, live GPS positioning & instant alerts.

Get on Google Play
Sponsored // Advertisement