Verified PartnerBengaluru–Chennai Expressway (NE-7) Route Map, Toll Rates, Status & Latest Updates (2026)
National Expressway 7 (NE-7) • Hoskote to Sriperumbudur Expressway
The Bengaluru Chennai Expressway (designated National Expressway 7 / NE-7 and also known as the Bangalore Chennai Expressway or Chennai Bangalore Expressway) is India's premier 261.7 km (262 km) four-lane access-controlled greenfield highway connecting Hoskote near Bengaluru to Sriperumbudur near Chennai across Karnataka (71.7 km), Andhra Pradesh (85.0 km), and Tamil Nadu (105.0 km), engineered to cut intercity transit time from 5–6 hours to under 3 hours.
- What is the Bengaluru Chennai Expressway?
- The Bengaluru–Chennai Expressway (NE-7) is a 261.7 km (262 km), 4-lane access-controlled greenfield expressway developed by NHAI under Bharatmala Pariyojana connecting Hoskote (Bengaluru) to Sriperumbudur (Chennai) with a design speed of 120 km/h.
- Is the Bengaluru Chennai Expressway open?
- Yes, the expressway is partially open to vehicular traffic. A continuous 96.7 km dual-carriageway stretch between Hoskote (Karnataka) and Byreddipalli (Andhra Pradesh) is fully operational with active FASTag electronic toll collection.
- How much of the expressway is operational?
- Approximately 96.7 km is operational, comprising all 71.7 km of Karnataka Phase 1 (Hoskote to Bethamangala) and ~25.0 km of Andhra Pradesh Phase 2 Package 1 (Bethamangala to Byreddipalli).
- When will the Bengaluru Chennai Expressway be completed?
- Full-corridor commissioning is realistically projected for 2027–2028. While balance AP and TN sections are in advanced execution, NHAI re-tendered Tamil Nadu Package 3 (Arakkonam–Kancheepuram, ₹633.12 Cr) under an 18-month EPC contract following contractor termination.
- What is the expressway route?
- The 262 km alignment traverses Hoskote → Malur → Bangarapet → Bethamangala (Karnataka) → Byreddipalli → Palamaner → Bangarupalem → Gudipala / Chittoor (Andhra Pradesh) → Walajahpet → Arakkonam → Kancheepuram → Sriperumbudur (Tamil Nadu), intersecting the Bengaluru Satellite Town Ring Road (STRR) and Chittoor–Thatchur Expressway (NH-716B).
Want Your Brand Featured Here?
Reach thousands of decision-makers and investors searching for infrastructure projects every month.
Bengaluru–Chennai Expressway Latest Update 2026
Recent progress across the 261.7 km Bengaluru–Chennai Expressway (National Expressway 7 / NE-7) demonstrates critical milestone achievements alongside key contract restructuring, transforming southern India's primary economic corridor. Developed under the Bharatmala Pariyojana program by the National Highways Authority of India (NHAI), this high-speed arterial connects seamlessly with other key mega-projects including the Bengaluru Satellite Town Ring Road (STRR), the upcoming Pune–Bengaluru Expressway, and the Bengaluru–Vijayawada Expressway.
In Karnataka, the entire 71.7 km Phase 1 stretch—comprising Packages 1, 2, and 3 from Hoskote through Malur and Bangarapet to Bethamangala—is 100% completed and open for vehicular traffic with operational FASTag tolling. Executed by Dilip Buildcon and KCC Buildcon with rigid 4-lane cement-concrete pavement, it has already shortened transit times between Bengaluru's eastern tech corridor and Kolar district.
In Andhra Pradesh, Phase 2 spanning approximately 85.0 km across Chittoor district has achieved a major milestone: Package 1 from Bethamangala up to Byreddipalli (~25.0 km) is open to traffic, extending the continuous operational length from Hoskote to approximately 96.7 km. The remaining two packages (Baireddipalle to Bangarupalem, 31.0 km, and Bangarupalem to Gudipala, 29.0 km) have attained 89% to 91% physical progress across major structures, grade separators, and mainline bituminous paving.
In Tamil Nadu, Phase 3 spans 105.0 km from the Andhra Pradesh border near Gudipala to Sriperumbudur. While Packages 1, 2, and 4 are advancing in civil execution (~79% to 85%), progress on Package 3 (Arakkonam to Kancheepuram, 25.5 km, Km 204.500 to Km 230.000) was disrupted after work stalled in May 2025 at approximately 53.56% physical progress (11.33 km completed) due to the financial default of the original concessionaire.
Bengaluru–Chennai Expressway Route
The greenfield corridor spans 261.7 km (officially rounded to 262 km) across three southern states—Karnataka (71.7 km), Andhra Pradesh (85.0 km), and Tamil Nadu (105.0 km). The alignment starts at Hoskote in Bengaluru Rural district, connecting directly with the Bengaluru Satellite Town Ring Road (STRR / NH-648) and Old Madras Road (NH-75), and terminates at Sriperumbudur on the western outskirts of Chennai, interfacing directly with NH-48 and the Chennai Peripheral Ring Road (CPRR).
Unlike the existing congested National Highway 48 (which runs through Hosur, Krishnagiri, Vaniyambadi, Ambur, and Ranipet over a circuitous 340+ km route), the NE-7 alignment takes a shorter, direct greenfield path north of the Eastern Ghat foothills, completely bypassing crowded urban bottlenecks.
Advertisement // Sponsor
Verified PartnerBengaluru Chennai Expressway Route Map
The interactive GIS map showcases the physical alignment, real-time package statuses, and coordinate path of the Bengaluru–Chennai Expressway (बेंगलुरु चेन्नई एक्सप्रेसवे रूट मैप). Users can view the exact geographic coordinate paths across Hoskote, Kolar, Chittoor, Ranipet, Kanchipuram, and Sriperumbudur, bypassing traditional congested state highways. This mapping interface displays contractor allocations, construction percentages, and package breakdowns for all 10 project stretches.
Advertisement // Sponsor
Verified PartnerBengaluru Chennai Expressway Opening Date & Current Status
The corridor is designed as an access-controlled expressway with an initial 4-lane cross-section (expandable up to 8 lanes) within a wide 90-meter Right of Way (RoW). Approximately 96.7 km is currently operational (Karnataka Phase 1 and AP Package 1 to Byreddipalli), while balance packages across Andhra Pradesh and Tamil Nadu are progressing through active civil execution and re-tendered balance works.
| Parameter | Technical Details |
|---|---|
| Project Name | Bengaluru–Chennai Expressway (National Expressway 7 / NE-7) |
| Total Length | 261.7 km (officially 262 km; 4-lane Access-Controlled, expandable to 8 lanes with 90m RoW) |
| Current Operational Length | ~96.7 km (Hoskote to Byreddipalli open to traffic) |
| Estimated Cost | ₹17,930 Cr (Bharatmala Pariyojana / National Expressway program) |
| Implementing Authority | National Highways Authority of India (NHAI) / MoRTH |
| States Covered | Karnataka (71.7 km), Andhra Pradesh (85.0 km), Tamil Nadu (105.0 km) |
| Major Connected Spurs | Chittoor–Thatchur Expressway (NH-716B) to Ennore & Kattupalli Ports, Bengaluru STRR (NH-648), CPRR & Parandur Airport Link |
| Current Phase | Partially Operational (96.7 km open; balance AP & TN packages in progress / re-tendered) |
| Start Date | November 2021 (Civil construction kicked off in Karnataka) |
| Expected Completion Date | Full corridor completion date is yet to be officially confirmed (18-month Package 3 balance works underway; 2027–2028 expected) |
| Total Construction Packages | 10 packages active across 3 execution phases |
| Notified Speed Limits | 120 km/h (Cars/LMVs) | 100 km/h (Buses) | 80 km/h (Trucks) under MoRTH Notification S.O. 1522(E) |
| Notified Toll Rates (Operational Section) | Closed tolling: ₹150 for cars (Hoskote–Bethamangala single), ₹225 (same-day return), ₹4,955 (monthly pass) |
Bengaluru Chennai Expressway Toll Charges 2026
Tolling operations across the open stretches of the Bengaluru–Chennai Expressway (NE-7) follow a modern distance-based closed tolling model via computerized FASTag Electronic Toll Collection (ETC). Vehicles are recorded at electronic entry gantries (such as Hoskote, Malur, Bangarapet, and Bethamangala) and charged only for the exact distance travelled upon exiting the expressway corridor.
Below is the officially notified NHAI user fee schedule currently applicable for the operational 71.7 km Karnataka stretch between Hoskote and Bethamangala:
Operational Closed-Loop Toll Plazas (Karnataka & Andhra Pradesh)
| # | Plaza Name | Chainage | State | Location & Closed-Loop Interchanges |
|---|---|---|---|---|
| 1 | Hedaginabele Toll Plaza | KM 0.000 | Karnataka | Located near Hoskote, this marks the western entry and exit point of the expressway. |
| 2 | Agrahara Toll Plaza | KM 27.500 | Karnataka | Positioned along the Hoskote–Malur route for vehicles entering or exiting near Malur. |
| 3 | Krishnavaram / Krishnarajapura Toll Plaza | KM 55.000 | Karnataka | Situated near BEML Nagar in Kolar Gold Fields (KGF) serving local logistics. |
| 4 | Sundarapalya Toll Plaza | KM 71.700 | Karnataka | Located in KGF taluk near Bethamangala, marking the completion of the 71.7-km Karnataka section. |
| 5 | Baireddypalle Toll Plaza | KM 96.700 | Andhra Pradesh | Covers the operational 25-km Andhra Pradesh stretch extending from the Karnataka border to Baireddypalle. |
Calculate Exact Toll Rates & Journey Price
Check single trip, return journey discounts, monthly pass tariffs, and per km pricing for Car, LCV, Bus, Truck, and Multi-Axle vehicles across all verified plazas on the Toll Calculator.
- M1 Passenger Vehicles (Cars / SUVs):120 km/h
- M2 & M3 Passenger Carriers (Buses):100 km/h
- N Category Freight Haulers (Trucks):80 km/h
To guarantee corridor safety at high design speeds, NHAI strictly prohibits two-wheelers (motorcycles, scooters), three-wheelers (auto-rickshaws, e-rickshaws), non-motorized vehicles, and agricultural tractors from entering the mainline expressway carriageway. Dedicated service roads serve local village traffic.
Bengaluru Chennai Expressway Package-Wise Construction Progress
The Bengaluru–Chennai Expressway is divided into 10 civil construction packages across three execution phases. Phase 1 in Karnataka (Packages 1–3, 71.7 km) is 100% completed and operational with computerized FASTag tolling. Phase 2 in Andhra Pradesh (Packages 1–3, 85.05 km) has achieved operational status up to Byreddipalli on Package 1, extending the continuous open corridor to ~96.7 km, with Packages 2 and 3 at 89%–91% physical progress. Phase 3 in Tamil Nadu (Packages 1–4, 106.1 km) has Packages 1, 2, and 4 under active civil execution (79%–85%), while Package 3 (Arakkonam–Kancheepuram, 25.5 km) was terminated following contractor financial default and re-tendered by NHAI under EPC mode for ₹633.12 Cr (Corrigendum 3 issued 27 October 2026, bid submission extended to 10 November 2026).
Packages 1, 2 & 3 fully completed by Dilip Buildcon and KCC Buildcon; tolling active from Hoskote to Bethamangala.
Package 1 open to Byreddipalli (~25 km); Packages 2 & 3 in advanced stages across Chittoor district with NH-716B interchange.
Packages 1, 2, 4 progressing smoothly. Package 3 re-tendered under fresh ₹633.12 Cr EPC contract (18-month execution period).
| Pkg Code | State & Stretch | Length | Contractor | Progress | Operational Status | Target |
|---|---|---|---|---|---|---|
| Phase 1: Karnataka (Total Length: 71.7 km — 100% Operational) | ||||||
| BCE-KA-PKG1 | Hoskote to MalurKm 0.000 to Km 26.400 (STRR Interchange) | 26.4 km(27.1 km with STRR links) | Dilip Buildcon Ltd. | 100% | Fully Operational | Open to Traffic |
| BCE-KA-PKG2 | Malur to BangarapetKm 26.400 to Km 53.500 | 27.1 km | Dilip Buildcon Ltd. | 100% | Fully Operational | Open to Traffic |
| BCE-KA-PKG3 | Bangarapet to BethamangalaKm 53.500 to Km 71.000 (AP Border) | 17.5 km(18.2 km incl. border link) | KCC Buildcon Pvt. Ltd. | 100% | Fully Operational | Open to Traffic |
| Phase 2: Andhra Pradesh (Total Length: 85.05 km — Chittoor District) | ||||||
| BCE-AP-PKG1 | Bethamangala to Byreddipalli | 25.05 km | Montecarlo Limited (MCL) | 96% | Open (~25 km) | Fully Operational |
| BCE-AP-PKG2 | Baireddipalle to Bangarupalem | 31.0 km | Apco Infratech Pvt. Ltd. | 89% | Under Construction | Mid 2026 |
| BCE-AP-PKG3 | Bangarupalem to Gudipala | 29.0 km | Dilip Buildcon Ltd. | 91% | Under Construction | Mid 2026 |
| Phase 3: Tamil Nadu (Total Length: 106.1 km — Ranipet, Vellore & Kanchipuram Districts) | ||||||
| BCE-TN-PKG1 | Gudipala to Walajahpet | 24.0 km | Montecarlo Limited | 81% | Under Construction | 2026–2027 |
| BCE-TN-PKG2 | Walajahpet to Arakkonam | 24.5 km | KCC Buildcon Pvt. Ltd. | 79% | Under Construction | 2026–2027 |
| BCE-TN-PKG3 | Arakkonam to KancheepuramKm 204.500 to Km 230.000 (Corrigendum 3: 27 Oct 2026) | 25.5 km | Fresh NHAI EPC Tender₹633.12 Cr / 18-month balance works (Bid close: 10 Nov 2026) | 54%11.33 km paved | Re-tendered | 2027–2028 |
| BCE-TN-PKG4 | Kancheepuram to SriperumbudurKm 230.000 to Km 261.700 (CPRR Junction) | 31.7 km(32.1 km DPR scope) | Chetak Enterprises / RCC Infra JV | 85% | Under Construction | 2026–2027 |
Bengaluru–Chennai Expressway Completion Date
The completion schedule of the Bengaluru–Chennai Expressway reflects a phased commissioning model. Phase 1 in Karnataka (71.7 km) is already open to public traffic. In Andhra Pradesh (Phase 2), all three packages spanning 85.0 km from Bethamangala to Gudipala are substantially advanced, with the stretch up to Byreddipalli already commissioned for traffic.
In Tamil Nadu (Phase 3), the critical path for completion centers around Package 3 (Arakkonam to Kancheepuram, 25.5 km), which faced execution delays and stoppage under the original concessionaire, D.P. Jain & Co. After contract termination, NHAI floated fresh EPC tenders valued at ₹633.12 crore with an 18-month construction period to execute remaining structures including 9 major bridges, 1 railway overbridge, and multiple underpasses. Full corridor completion date is yet to be officially confirmed, with completion realistically anticipated in 2027–2028.
Chittoor–Thatchur Spur, Port Connectivity & Logistics Impact
A major highlight of the Bengaluru–Chennai Expressway is its strategic multi-modal freight connectivity. Near Chittoor in Andhra Pradesh, the alignment intersects directly with the 116 km under-construction Chittoor–Thatchur Greenfield Expressway (NH-716B), which also connects towards the Surat–Chennai Expressway economic corridor.
This dedicated freight spur allows heavy container trailers and commercial logistics fleets travelling between Bengaluru's manufacturing clusters (Peenya, Hoskote, Bidadi, Narasapura) to bypass Chennai's congested inner ring roads completely. Cargo trucks can proceed directly toward Kamarajar Port (Ennore) and Kattupalli Port in North Chennai. Additionally, the eastern terminus at Sriperumbudur links directly into the auto-manufacturing corridor of Sriperumbudur-Oragadam and the proposed Parandur International Greenfield Airport near Kanchipuram.
Bangalore to Chennai Expressway Travel Time & Distance
Travel time reduction between Karnataka and Tamil Nadu is the primary socioeconomic benefit of the project. Currently, road commuters between Bengaluru and Chennai rely on NH-48 (via Hosur, Krishnagiri, Vellore, and Ranipet) or NH-75 (via Kolar, Chittoor, and Ranipet), covering between 330 km and 350 km. Due to heavy traffic congestion, industrial freight density, and multiple toll plazas, this journey typically requires 5 to 6 hours by car and over 7 to 8 hours by bus or truck.
Once the 262 km Bengaluru–Chennai Expressway is fully commissioned, travel time will drop to approximately 2.5 to 3 hours at a continuous design speed of 120 km/h. By cutting nearly 80 km off the travel distance and eliminating all urban bottlenecks, the corridor will slash fuel consumption, lower logistics transport costs by over 20%, and facilitate same-day turnarounds for commercial fleets.
Advertisement // Sponsor
Verified PartnerBengaluru Chennai Expressway Latest News
Video Updates
Advertisement // Sponsor
Verified PartnerFrequently Asked Questions
Related Infrastructure Projects
Bengaluru Satellite Town Ring Road (STRR)
An approximately 280 km access-controlled 4/6-lane access-controlled highway bypass connecting key towns and industrial belts around metropolitan Bengaluru across Karnataka and Tamil Nadu.
View Project →Chittoor Thatchur Expressway
An approximately 116.1 km six-lane, access-controlled greenfield corridor designed to enhance connectivity between Keenatampalli in Andhra Pradesh and Thatchur in Tamil Nadu.
View Project →Surat Chennai Expressway
A massive greenfield and brownfield economic corridor linking Surat in Gujarat to Chennai in Tamil Nadu, passing through Maharashtra, Karnataka, Telangana, and Andhra Pradesh.
View Project →Coimbatore Bengaluru Expressway
A proposed approximately 250 km access-controlled highway bypass corridor designed to connect Bengaluru and Coimbatore via Erode, Salem, and Hosur.