Verified PartnerBaihata Chariali–Tezpur 4-Lane Highway (NH-15) Route Map, Status & Latest Updates (2026)
Traversing Kamrup, Darrang, and Sonitpur on the north bank of the Brahmaputra River, this four-laning corridor will significantly reduce travel time, alleviate chronic congestion, and enhance high-speed freight mobility between Guwahati and Tezpur, unlocking economic growth across agro-industrial centers, tea plantations, and strategic defense logistics into Arunachal Pradesh.
"The Baihata Chariali–Tezpur 4-Lane Highway Project is a transformative 135.87 km access-controlled four-laning highway along NH-15 in Assam, approved by the Cabinet Committee on Economic Affairs (CCEA) chaired by Prime Minister Narendra Modi with a total capital cost of ₹8,970.20 Crore (including civil construction cost of ₹7,642.20 Crore). Executed by NHIDCL on Build-Operate-Transfer (BOT) Toll mode, the project modernizes the northern bank trunk artery of the Brahmaputra River from Baihata Chariali (Ch. 0+000) near Guwahati to Tezpur (Ch. 150+971). The corridor incorporates 5 major bypasses (58.7 km), a 4.90 km emergency landing airstrip (ELF) for Indian Air Force fighter aircraft, an integrated 1,136-meter wildlife elephant underpass & ROB, 15 major bridges, and 3 major interchanges."
Want Your Brand Featured Here?
Reach thousands of decision-makers and investors searching for infrastructure projects every month.
Advertisement // Sponsor
Verified PartnerRoute Map & NH-15 Alignment
Explore the 135.87 km 4-lane access-controlled Baihata Chariali–Tezpur Highway corridor along NH-15 in Assam. The route bypasses congested urban settlements across 5 major greenfield bypasses (58.7 km total), incorporates an Indian Air Force (IAF) 4.90 km Emergency Landing Facility (ELF) on the Tezpur bypass, provides a dedicated elephant underpass, and links Kamrup, Darrang, and Sonitpur districts. The 15.11 km Mangaldoi Bypass is being executed under a separate standalone contract.
Advertisement // Sponsor
Verified PartnerProject Cost & Technical Specifications
4-Lane Highway Concession Package: Baihata Chariali to Tezpur (135.87 km Net Length)
National Highways and Infrastructure Development Corporation Limited (NHIDCL) / MoRTH / Ministry of Road Transport and Highways (MoRTH) • Tender ID: 2026_NHIDC_921000_1| Parameter | Official Primary Specification |
|---|---|
| Official Project Scope | Construction of 4 Lane Highway from Baihata Chariali (Ch. 0+000), near Guwahati to Tezpur (Ch. 150+971) excluding Mangaldoi Bypass along NH-15 in Assam on BOT Toll Mode |
| Approving Authority | Cabinet Committee on Economic Affairs (CCEA), chaired by Prime Minister Narendra Modi (Approved on 6 August 2026) |
| Approved Capital Outlay | ₹8,970.20 Crore |
| Civil Tender Value & EMD | ₹7,642.20 Crore (excl. GST) | Earnest Money Deposit (EMD): ₹76.42 Crore |
| Tender Reference ID | Tender ID: 2026_NHIDC_921000_1 (NIT Ref: NHIDCL/Assam/2025/BaihataCharialitoMissionChariali/260456) |
| Tender Bidding Deadlines | Bid Submission Deadline: 27 November 2026 • Technical Bid Opening: 28 November 2026 |
| Net Corridor Length | 135.87 km (Excluding the 15.11 km standalone Mangaldoi Bypass) |
| Execution & Delivery Model | Build-Operate-Transfer (BOT) Toll Mode under NH(O) Programme |
| Implementing Authority | National Highways & Infrastructure Development Corporation Limited (NHIDCL) / MoRTH |
| 5 Major Bypasses (58.7 km) | 5 Major Bypasses (58.7 km): Baihata Chariali (7.2 km), Sipajhar (9.8 km), Kharupetia (8.3 km), Dhekiajuli (5.4 km), Mission Chariali / Tezpur Ring (27.7 km) |
| Emergency Landing Facility (ELF) | 4.90 km long airstrip on Tezpur Bypass developed in coordination with the Indian Air Force (IAF) |
| Wildlife Preservation Structure | Dedicated Elephant Underpass (EUP) (1,136m integrated EUP & ROB) in Sonitpur / Darrang |
| Bridges & Crossings Count | 15 Major Bridges • 30 Minor Bridges • 19 Flyovers • 46 Underpasses (Vehicular & Pedestrian) |
| Service Roads | 210 km of dedicated 2-lane service roads to segregate local transit from high-speed traffic |
| Grade-Separated Interchanges | 3 Major Interchanges: Interchanges connecting with NH-27 at Baihata Chariali, upcoming Guwahati Ring Road, and NH-715 at Tezpur |
| Contract Construction Period | 1,095 Days from Appointed Date (36 Months) |
| Current Construction Status | Tendering & Land Acquisition Stage — Bidding underway; Physical construction has not yet commenced |
Corridor Alignment & Engineering Scope
Guwahati–Tezpur Trunk Corridor (NH-15)
National Highway 15 (NH-15) functions as the vital north-bank economic lifeline connecting Guwahati with the central and eastern districts of Assam and onwards to Arunachal Pradesh. The project upgrades the corridor from Baihata Chariali (Ch. 0+000) to Tezpur (Ch. 150+971) into a 4-lane access-controlled dual carriageway over a net project length of 135.87 km. The 15.11 km Mangaldoi Bypass is being executed under a separate standalone contract.
5 Major Bypasses Decongesting Urban Settlements (58.7 km Total)
To eliminate bottlenecks and chronic congestion across commercial centers along the old alignment, the project incorporates 5 major greenfield bypasses totaling 58.7 km: Dumunichowki, Mangaldoi, Sipajhar, Kharupetia, Dhekiajuli. This segregation allows long-distance freight and passenger transit to bypass dense settlements while local commuters use dedicated service lanes.
Emergency Landing Facility (ELF) for Indian Air Force (4.90 km)
As part of strategic defense infrastructure enhancement in the North East, the project includes a 4.90 km long Emergency Landing Facility (ELF) airstrip on the Tezpur Bypass section. Finalized in close coordination with the Indian Air Force (IAF), this reinforced dual-use section can accommodate military fighter jet and transport operations during defense contingencies and emergency humanitarian disaster response.
Dedicated Elephant Underpass & Wildlife Mitigation
Traversing ecologically sensitive regions adjacent to forest tracts and wildlife habitats in Sonitpur and Darrang, the alignment incorporates a dedicated Elephant Underpass (EUP) and wildlife eco-passages. Engineered to prevent vehicular collisions with Asian elephant herds along their traditional migration corridors, these structures provide safe passage with naturalized earthen beds and acoustic shielding.
Comprehensive Bridge, Flyover & Service Road Infrastructure (210 km)
To handle the complex hydrology of the Brahmaputra floodplain and ensure uninterrupted high-speed movement, the engineering scope encompasses 15 major bridges, 30 minor bridges, 19 flyovers, 46 underpasses, and an extensive network of 210 km of 2-lane service roads. Three major grade-separated interchanges provide seamless access to NH-27 at Baihata Chariali, the upcoming Guwahati Ring Road, and NH-715 at Tezpur.
Concession Model & Procurement Timeline
Sanctioned under the Build-Operate-Transfer (BOT) mode under the National Highways (Original) [NH(O)] programme, the project is being tendered by NHIDCL under Tender ID 2026_NHIDC_921000_1 with an estimated civil value of ₹7,642.20 Crore (excl. GST). Bid submission closes on 30 November 2026 (15:00 IST). The contract stipulates a construction period of 1,095 Days from Appointed Date (36 Months) following financial close and encumbrance-free Right of Way handover.
Advertisement // Sponsor
Verified PartnerLatest Baihata Chariali–Tezpur Highway News & Updates
Video Updates
Cabinet Clearance, Procurement & Construction Timeline
Cabinet Clearance & Sanction Approved
The Cabinet Committee on Economic Affairs (CCEA), chaired by Prime Minister Narendra Modi, approved the ₹8,970.20 Crore 4-laning project under BOT mode.
Global Notice Inviting Tender (NIT) Issued
NHIDCL issued national competitive bids under Tender ID 2026_NHIDC_921000_1 for the 135.87 km net corridor with ₹7,642.20 Crore estimated civil value.
Bid Submission & Technical Opening
Concessionaire bid submission deadline at 15:00 IST, followed by technical evaluation for qualification of EPC/BOT developers.
Concession Agreement & Financial Close
Formal award of concession, equity tie-up, financial close, and notification of the official Appointed Date by NHIDCL / MoRTH.
Target Commercial Operations Date (COD)
Target completion and commissioning of the 4-lane access-controlled highway within the 1,095-day contractual construction window.
Advertisement // Sponsor
Verified PartnerFrequently Asked Questions (FAQs)
The Baihata Chariali–Tezpur 4-Lane Highway Project is a 135.87 km four-laning access-controlled highway project along NH-15 in Assam, approved by the Cabinet Committee on Economic Affairs (CCEA) with a total capital cost of ₹8,970.20 Crore (civil construction cost of ₹7,642.20 Crore). Executed by NHIDCL on DBFOT / Concession mode, the project connects Baihata Chariali near Guwahati to Tezpur, bypassing major congested towns.
The total corridor chainage spans 150.971 km, with a net project length of 135.87 km (the 15.1 km Mangaldoi Bypass is being executed under a separate package). The project incorporates 5 major bypasses totaling 58.7 km: Baihata Chariali (7.2 km), Sipajhar (9.8 km), Kharupetia (8.3 km), Dhekiajuli (5.4 km), and Mission Chariali / Tezpur Ring Corridor (27.7 km).
Yes. The corridor features a 4.90 km heavy-duty Emergency Landing Facility (ELF) between Ch 125+900 and Ch 130+800 with rigid concrete pavement, blast pads, and an ATC apron designed for Indian Air Force (IAF) fighter jet and transport aircraft operations during defense emergencies and humanitarian crises.
The alignment features an integrated 1,136-meter mega-structure between Ch 133+704 and Ch 134+840 that combines a Rail Over Bridge (ROB) and an extensive 29×35m dedicated Elephant Underpass (EUP) with 7.0-meter vertical clearance, acoustic shielding, and naturalized vegetation to ensure seamless, safe migration for Asian elephant herds.
The project is being developed under the Build-Operate-Transfer (BOT) Toll mode under the National Highways (Original) [NH(O)] programme by NHIDCL. The construction period is 1,095 days (36 months / 3 years) from the Appointed Date.
The project includes 15 major bridges, 30 minor bridges and 19 flyovers. These structures are designed to improve traffic movement, provide grade-separated crossings and maintain connectivity across the 135.87 km four-lane corridor.
The highway development includes 46 underpasses to facilitate local traffic movement and crossings across the access-controlled corridor. An elephant underpass is also specifically planned in the Tezpur Bypass to address wildlife movement.
The project provides for approximately 210 km of service roads. These roads are intended to maintain access to adjoining settlements, properties and local roads while reducing direct interference between local traffic and high-speed highway traffic.
The corridor is planned to connect with 8 PM GatiShakti economic nodes, 2 social nodes, 3 tourist nodes and 7 logistics nodes. This connectivity is expected to improve access to important economic activities, public facilities, tourism destinations and freight transportation infrastructure across Assam and adjoining regions.
Yes. According to the Ministry of Road Transport and Highways, the corridor's connectivity network includes 3 major railway stations, 2 airports and 2 waterway terminals. These multimodal connections are expected to strengthen passenger movement and freight transportation across the region.
The four-lane corridor is expected to improve transportation between tea-producing areas, processing facilities, commercial centres and markets. Better highway connectivity can support the movement of agricultural products, industrial goods and freight while improving access to trade and logistics networks across Assam and neighbouring regions.
Yes. The Guwahati–Tezpur Corridor is expected to help decongest the existing NH-27 East-West Corridor along the southern bank of the Brahmaputra. By improving connectivity between Baihata Chariali and Tezpur and providing bypasses around congested towns, the project is intended to improve regional traffic distribution.
No. The 15.11 km Mangaldoi Bypass is specifically excluded from the 135.87 km Baihata Chariali–Tezpur four-laning project. The overall corridor chainage extends from Ch. 0+000 at Baihata Chariali to Ch. 150+971 at Tezpur, with the Mangaldoi Bypass section being handled separately.
The Guwahati–Tezpur Corridor is expected to strengthen regional connectivity across Assam and improve access to important economic, logistics and transport nodes serving neighbouring Arunachal Pradesh. Improved road infrastructure will support passenger travel, freight movement, tourism and access to markets in the northeastern region.
Related Infrastructure Projects
Tapka–Karu–Sering–Bangan Greenfield Road
An 81.686 km 2-lane strategic greenfield highway corridor built to National Highway and State Lane (NHSL) specifications in the Kurung Kumey district by Border Roads Organisation (BRO Project Arunank).
View Project →Fotu La Twin Tunnel Project
Construction of uni-directional twin tunnels (~1.96 km each) with approach roads totaling 2.65 km bypassing the 4,108m Fotu La Pass on NH-01 (Leh–Kargil Highway) in Ladakh by MoRTH and BRO.
View Project →Delhi–Dehradun Expressway
A 213 km 6-lane access-controlled expressway connecting Delhi NCR to Dehradun via Saharanpur with a 12 km elevated wildlife corridor over Rajaji National Park.
View Project →Amritsar–Jamnagar Expressway
A 1,257 km economic corridor and greenfield-brownfield expressway connecting Amritsar in Punjab to Jamnagar in Gujarat across Punjab, Haryana, Rajasthan, and Gujarat.